• To Perform Inspections of Cable Laying, Cable CTIR (continuity Test Insulation Resistance), Hi-Pot test of Cables and Cable Terminations with Contractor and Client.
• Preparing the test results sheet and reporting to manager.
• Weekly RFIs summary updating and reporting to manager Co-ordination with Client
• MV/LV Motor solo run test performed.
• HI-Pot Test of MV Cables, IR, WR test of LV/MV motors.
• Conduit work for Power and control cables.
• Installed and monitored Local control station work activity.
• Verified Cable Tray route and made necessary changes as per site situation.
• Ensure compliance with safety requirements and standards procedures.
• Investigate problems and recommend solutions.
• To ensure that the work is being done according to WPP (work plan procedure).
• To ensure that the inspections being done according to ITP (Inspections and Test Plan).
Education
Bachelors in Electrical Engineering(Power)
Sep 2011
— Jun 2015
Experience
Internee
Aug 2015
— Sep 2015
QA/QC Engineer (E&I)
Jun 2015
— Apr 2016
ARL is the pioneer of crude oil refinery and supplying of refined petroleum products. Project Up gradation comprises of Pre-Flash Naphtha Isomerization unit, Diesel Hydro Desulphurization (DHDS) unit, expansion of existing power plant, Ammine Unit and Sulphur Recovery Unit.
• To perform inspections after installation of Cable Tray, Conduit work, lighting and small power systems, Grounding and lighting protection system, Fire Alarm, Electrical Equipment’s (Local Control Station, Panels), CCTV, communication system with Contractor and Client.
• To Perform Inspections of Cable Laying, Cable CTIR (continuity Test Insulation Resistance), Hi-Pot test of Cables and Cable Terminations with Contractor and Client.
• Preparing the test results sheet and reporting to manager.
• Weekly RFIs summary updating and reporting to manager Co-ordination with Client
• MV/LV Motor solo run test performed.
• HI-Pot Test of MV Cables, IR, WR test of LV/MV motors.
• Conduit work for Power and control cables.
• Installed and monitored Local control station work activity.
• Verified Cable Tray route and made necessary changes as per site situation.
• Ensure compliance with safety requirements and standards procedures.
• Investigate problems and recommend solutions.
• To ensure that the work is being done according to WPP (work plan procedure).
• To ensure that the inspections being done according to ITP (Inspections and Test Plan).