Management of Project Control / Project Services / Project Planning


Last Updated: 17th April 2018 (over 4 years ago)

Address
Austria

E-mail
Locked

Phone Number
Locked

Gender
Male

Age Range
55 to 64

Qualification Level
Trade Qualification

Languages
Dutch, English, German

Summary

Over 30 years of experience in Project Management, with 15 years in a Leadership role. Gained experience in various industries (Petrochemical, Refinery, Power and Mining) in all the phases of a project from FEED to Hand-Over, taking responsibility for different execution roles in several multi-disciplinary environments like EPC, EPCM, Integrated Teams, Construction Contractors and Operators alike.
Worked and lived in a multitude of geographic locations and continents with exposure to some of the world’s biggest multibillion dollars projects. Key competencies include strong analytical skills, multi-cultural team’s leadership, strong process implementation and management, organizational ability, quick learning, delegating and carrying responsibility, capacity to work under pressure and meeting deadlines, excellent public relations skills and a conscious approach to HSSE.

Experience

Petroliam Nasional Berhad (PETRONAS), Malaysia
Head Project Control

   Dec 2014
— Jul 2017

Refinery And Petrochemicals Integrated Development (RAPID) Project
RAPID Project, a world-scale integrated refinery and petrochemical complex. The proposed refinery will have a capacity of 300,000 barrels per standard day and will supply naphtha and liquid petroleum gas feedstock for the RAPID petrochemical complex, as well as produce gasoline and diesel that meet European specifications.
The petrochemical units, on the other hand, will enhance the value of the olefin streams coming from the RAPID steam cracker by producing various merchant grades petrochemicals products such as polyethylene, polypropylene, synthetic rubbers and other petrochemicals products.

http://www.epcengineer.com/projects/details/2342/refinery-and-petrochemicals-integrated-development-rapid-project (last accessed 15.Dec.2014)

Responsible for the establishment of Project Control Strategy by managing and monitoring the implementation of an effective integrated project planning and controls at programme level for RAPID project covering refinery, SCC, petrochemicals and its associated facilities as well as other interface projects by adopting project controls best practices and promoting effective communication among technical and commercial teams in order to ensure this strategy is adopted timely and implemented for safe, quality and cost-effective project execution as well as aligned with business objectives.

Driving in instilling HSE culture into project team members by ensuring compliance to statutory requirements and specific HSE policy, standards and documents in all aspects of project planning control activities in order to address socio-economic impact on surrounding populations while fulfilling the national regulatory requirement.

Manage and inculcate project governance through establishment of applicable project management compliance system, risk mitigation and value leakage prevention programs to assure consistency and transparency in project execution.

Drive and plan the incorporation of project risks mitigation activities into project planning and scheduling activities and cost estimates and lead schedule and cost risk assessment using Primavera. Recommend the integrated QRA framework through identification of risk factors/drivers and assigning of risk impact ranges to the identified schedule and cost components in identifying overall risk probabilities and establishing deterministic completion probabilities for effective quantification of schedule risks and contingency cost estimate and development of mitigation measures in line with standard PPMS implementation in ascertaining improved control of project performance.

Lead and drive project management control activities by consolidating all major milestones from RAPIDs technical and commercial teams, project management team and third parties as well as anticipating any deliverables shortcomings to ensure project deliverables are achieved within budgeted cost and schedule.

Enforce the implementation of applicable PETRONAS procedures and guidelines and affect the compliance to statutory and legislative requirements to ensure conformance to the established ‘Limits of Authority’ to safeguard PETRONAS interest, image and reputation.

Drive the development of a competent working team that will enhance and sustain staff capabilities in achieving high performance delivery to ensure the right leadership and capabilities in executing their jobs.

Develop and implement distinctive mindset, behavior and culture to achieve high work performance by adopting and implementation of value interventions, tools and methodologies to promote and instill high sense of commitment, ownership, integrity and loyalty that will contribute to operational excellence.

Linde AG, Germany
Project Control Manager

   Feb 2013
— Nov 2014

Appointed to take over from previous position holder to improve project control
Project: Reliquification LNG- and Nitrogen Generation- Plant
The project encompasses the build of a mid-scale natural gas liquefaction plant. The new boil-off gas reliquefaction plant has a maximum design capacity of 1,840 tonnes of liquefied natural gas (LNG) per day and is located in the Bintulu LNG complex in the state of Sarawak in eastern Malaysia. Linde is responsible for the detail engineering, procurement, construction and installation of the new plant.
Take responsibility for the improvement and implementation of an overall project re-baseline schedule including, but not limited to, weekly and monthly progress reporting. Liaise with site management to ensure all aspects with regard to the project control functions on scheduling, cost, estimation and change are addressed in accordance with the existing procedures. Change or add procedures where necessary and establish close cooperation between the project control department and claims management department to ensure full compliance with the contract. Support the control team in the setup of the Pre- Commissioning planning to establish a full integrated project schedule.

Teekay Petrojarl
Project Control Consultant

   Jan 2012
— Jan 2014

Project: Hamburg – BANF- FPSO Reinstatement and Reclassification Project
Responsible to ensure proper development and implementation of the overall project schedule, adaptation of existing, internal, procedures and work methods to align with those common in the yard. Establish WBS, project reporting on cost and progress and ensure baseline schedule and budget approval. Further updates and follow up to be continued with a reduced team thereafter.

LINDE AG
Project Control Manager

   Jun 2010
— Jan 2012

2011 - 2012 [Tobolsk, Russian Federation]
Appointed to take over from previous position holder to improve project control
Project: Tobolsk - Polypropylene Plant
Take responsibility for the improvement and implementation of an overall project re-baseline schedule including, but not limited to, weekly and monthly progress reporting. Liaise with site management to ensure all aspects with regard to the project control functions on scheduling, cost, estimation and change are addressed in accordance with the existing procedures. Change or add procedures where necessary and establish close cooperation between the project control department and claims management department to ensure full compliance with the latest contract amendment. Support the control team in the setup of the Pre- Commissioning planning to establish a full integrated project schedule.

2011 Project Control Audit [Pullach, GERMANY]
Project: Tobolsk - Polypropylene Plant
Execute a site audit on the project control department engaged with the "Tobolsk Polypropylene Plant" in the Tyumen area in Russia. Check the current processes in place are aligned to the contractual and project specific environmental needs. To see if all tools are installed correctly and al interfaces are working properly. Have a feasibility check on the current schedule (baseline) the workings in its current structure and make recommendations to eliminate vulnerabilities, improve schedule(s), simplify processes, where needed.

2010 to 2011 Schedule Analyst / Project Control Manager [Ras Laffan, QATAR]
Appointed to take over from previous position holder to improve project control
Qatar SHELL Pearl GTL Project [Construction of the world's largest gas to liquids (GTL) plant]: Construction of the world’s largest air separation plants, to be handed over turn-key by the end of 2011.
Schedule Analysis in support of the claim for prolongation of the project which has been successfully concluded in additional fund and EOT for the project
Responsible for the continued development and implementation of an overall project rebaseline schedule including management of all aspects with regard to the project control functions of scheduling, cost, estimation and change. Encourage close cooperation between the control and contracts department to ensure full compliance with the latest contract amendment. Support the control team in switching from construction phase to Pre- Commissioning phase.

TECHNIP
Site Planning Manager

   Mar 2005
— Jun 2010

2008 to 2010 HO Planning Manager, Technip Geoproduction [Kuala Lumpur, Malaysia]

2009 to 2010 Project: Weda Bay Nickel Project, Indonesia
Responsible for the development and implementation of an overall project schedule for the BFS for this Nickel Mine Project. Emphasis on preliminary Construction Schedule during the awarded the BFS (Bankable Feasibility Study) Detailed Design and Engineering Phase of the project with the use of P6.2.

2008 to 2009 Project: Koniambo Nickel Project, New Caledonia
Responsible for the continued development and implementation of an overall project schedule for this Nickel Mine Project. Emphasis on preliminary Construction Schedule during the Detailed Design and Engineering Phase of the project with the use of P6.2. Technip, being leader in a Joint Venture with Hatch, has been awarded a reimbursable contract for the engineering, procurement and construction of Koniambo Nickel Mine to be located in Kone, north of New Caledonia.

2007 to 2008 Site Planning Manager, TECHNIP Consortium [Dung Quat, Vietnam]
Appointed to take over from previous position holder to improve project control
Project: Petrovietnam Dung Quat Refinery Project, Vietnam
Responsible for the continued development and implementation of the then existing overall project schedule for this Refinery Project. Technip, being leader in a consortium with JGC and Tecnicas Reunidas, has been awarded a lump sum turnkey contract for the engineering, procurement and construction of Vietnam’s first crude oil refinery to be located in Dung Quat, south of Da Nang in central Vietnam.
The project includes utilities, off sites, the refinery and the crude oil import facilities. This refinery is designed to have a processing capacity of 145,000 BPSD and Technip’s engineering centers in Paris (France) and in Kuala Lumpur (Malaysia) carried out the engineering, procurement and construction contract.

2005 to 2007 Site Planning Manager, CTJV (Chiyoda-Technip Joint Venture) [Ras Laffan, Qatar]
Appointed to take over from previous position holder to improve project control
Project: QatarGas II Project
Responsible for the continued development and maintain the overall construction schedule for this huge project in which 64000 tons of piping require 4000000 Dia Inch to be welded and 5000 ton of supports to be fabricated which will connect 1400 pieces of equipment resting on 215000 m3 of concrete. For this the organization is made up of 7 area planners 3 scheduling engineers and 3 senior scheduling engineers.
The existing QatarGas plant consists of three (3) LNG trains with a rated design capacity of 9.0 MMTPA LNG with associated utilities, off-plots, off-sites and infrastructure. This existing plant is named QatarGas I, and owned by Qatar Petroleum (QP), Total and Exxon-Mobil.
The owners and funds are different for QatarGas II. This expansion project adds two (2) additional very large LNG trains which will provide an additional 15.6 MMTPA of LNG (FOB Ras Laffan), with associated utilities, off-sites and off-plots.