
Electrical Engineer
Last Updated: 27th May 2017 (over 5 years ago)
Summary
Specialties
Power Engineering,Technical Specifications of all electrical equipment, Junction Boxes, Zoning and Cable Tray Routing ,Light load calculation, Cable Sizing, Lighting System and Lighting Pole ,International Standards such as IEEE Guide 80 and IEC 60909 ,Calculation and placement of transformers, Placement of 11 kV electric poles light and lighting of the roads,Preparation of BOQ’s ,Site supervision,Load calculations for transformers, generators and submersible pumps, Power factor panel calculations, Voltage drop calculations and ELV systems as per IEC and BS standards.
Education
Electrical Engineer
Sep 2005
— Sep 2009
ELECT/28981
Experience
Electrical Engineer
May 2014
— Apr 2017
• Light load calculation, Cable Sizing, Lighting System of the Sulimanki barrage Site Colony
• Review of Technical Specifications of all electrical equipment to be installed
• Review of all electrical drawings with respect to control building structures and SCADA system
• Single Line Diagrams for Distribution, Main Panel Board and Local Control Pannel
• Review of drawings for Fire Protection System
• Load Balancing and Circuit Breaker Sizing
• Providing the Earthing of Electrical system and Lightening protection system
• Placement of 11 kV feeder for barrage and colony
• Lighting of the roads and barrage in compliance with the standard LUX levels
Electrical Engineer
Dec 2011
— May 2014
• Development of electrical drawings for Dasu site colony which included load flow, calculation and placement of transformers, placement of 11 kV electric poles light and lighting of the roads
• Development of electrical drawings for Transformer/GIS cavern, Power House and the takeoff yard
• Routing of 132 kV transmission line and spotting of towers from Dubair Khwar to Dasu
• Light load calculation, Cable Sizing, Lighting System and Lighting Pole of the entire dam including of Spillway, Take-off yard, Power house, Access tunnel, GIL tunnel and IPB shaft
• Fire alarm and CCTV system in the power house
• Junction Boxes, Zoning and Cable Tray Routing in the Powerhouse
• Complete understanding of International Standards such as IEEE Guide 80 and IEC 60909 pertaining to substation grounding and estimation of fault current
• Designing of a complex earthing grid to ensure tolerable touch and step voltages
• Preparation of BOQ and Bidding document for the powerhouse
Project Engineer (Electrical)
Sep 2009
— Nov 2011
As a Project Engineer (MEP), I worked at different projects including the construction of Extension of Punjab Assembly, Tax House Building, and Lahore College for Women University. Key responsibilities included:
• Resource allocation (manpower, materials, equipment tools and consumables)
• Development of timelines for project tasks and ensuring these timelines were met
• Development of a skill matrix so that the right man is placed on the right job
• Interpretation of engineering drawings and developing a complete understanding of all specifications and standards that needed to be met
• Constant site supervision to ensure quality of work and ensuring that safety standards were met
• Submission of daily reports entailing progress made during the previous day, problems faced if any and possible ways to mitigate these issues and risks