IIT Roorkee graduate with 18+ yrs industry experience covering EPC business in Power and Oil & Gas


Last Updated: 27th February 2018 (over 4 years ago)

Address
India

E-mail
Locked

Phone Number
Locked

Gender
Male

Age Range
35 to 44

Qualification Level
Degree

Languages
English, Hindi

Summary

• Experienced in leading project activities starting from engineering proposal & cost estimation at tendering stage and going up to engineering support during erection and commissioning. This includes complying project contract, basic engineering package, technical specifications, detail engineering, bid evaluation, Technical recommendation, vendor document review, FAT, erection and commissioning support, as built documentation , customer punch point resolution and closing of supply and service contracts
• Experienced in milestone planning, estimating engineering efforts, managing engineering progress, formulating trends for variations in man-hours efforts/ material quantities/project schedule, tracking material requisitions and controlling vendor documents review cycle.
• Exposed to extensive co-ordination with project sites, vendors, customers, customer’s consultants, erection contractors, procurement and project management groups.
• Experienced in proposal engineering and cost estimation for power projects and FEED for oil & Gas projects.
• Good technical oversight of mechanical/electrical equipments, mechanical auxiliaries, mechanical process and Interdisciplinary interfaces between C&I, mechanical, electrical and piping.
• Successfully supported designers for 3D design efforts related to C&I engineering.
• Understanding of international codes like ISA/ASME/ISO
• Successfully lead and supervise the Teams for engineering execution on multiple projects.
• Experienced in Factory Acceptance tests
• Visited project sites for more than 10 times at different stages of the projects and spent lot of time on sites in supporting erection & commissioning teams, and closing customer punch points.

Education

University of Roorkee (Now IIT Roorkee)
B.E (Electronics & Communication)

   Jul 1995
— May 1999

Experience

Sardeva Management consultants private limited
Head – Business Development and Multidisplinary Management Consultancy

   Oct 2017
— Current

• Business Development and Execution on the following
 DPR assignment in infrastructure industry and municipal corporation
 Technical consultancy assignments in waste treatment industry i.e. waste to energy & waste to compost.
• Empanelment with Govt. agencies
• Establish Joint ventures for bidding and empanelment
• Empanelment with Banks for TEVs and Valuation
• Develop a Technical consultancy and Project management consultancy set-ups

LANCO Infratech Limited
Assistant General Manager (C&I)

   Dec 2016
— Sep 2017

1 X 660 MW Supercritical Ennore Thermal Power Station Expansion Project (EPC Project)
• Co-ordination with Owner, Owner’s Engineer (Desein), Project site erection and commissioning teams, Project controls, Procurement, Quality department and EPC Management.
• Finalization of engineering consultant for detail engineering work. Coordination with engineering consultant (Fitchner). Tracking and approving progress reports for consultant payments against milestones.
• Participation in CEO and Dy.CEO review meetings.
• Review and Finalization of P&ID’s and process write-ups.
• Tracking of Material requisition Milestones and cost vis-à-vis estimated budget.
• Technical oversight, guidance and approval for Team’s detail engineering activities.
• Supervising Team for Technical Specification preparation, Bid Evaluation and Drawing/Calculations review for Steam and Water Analysis System (SWAS), VMS and DDCMIS.
• Dealing C&I Engineering for Boiler, Steam turbine and associated auxiliaries.
• Responsible for Interfaces with Mechanical, Electrical and Civil Engineering.

BECHTEL
Deputy Engineering Group Supervisor (CS)

   Aug 2012
— Sep 2016

Shell Franklin - Gas to Chemical derivatives Project (Sept 2015 – Sept 2016)
• Project lead responsibilities like Co-ordination with Project management, Project controls, Procurement, Customer, Project site, Quality department and Engineering management.
• Responsible for project control activities Like L3 schedule, Engineering Progress and Performance report (EPPR) , Short term work plan (STWP) and Trends
• Tracking of Material requisition Milestones and engineering quantities vis-à-vis estimated quantities.
• Planning of WBS wise 3D-Model development Plan for OSBL & Cogen/CWT area, leading 3D design efforts for OSBL and Cogen area.
• Approver/Checker of engineering deliverables like Material requisitions, data sheets and Interfaces list.
• Responsible C&I engineer for Mechanical packages - performing bid evaluation, vendor discussion and vendor print reviews.
ARBEEL Power Station (Conversion to CCPP) and Panda Stonewall CCPP (Nov 2012 – Sept 2015)
• Project lead responsibilities like Co-ordination with Project management, Project controls, Procurement, Customer, Project site, Quality department and Engineering management.
• Responsible for project control activities Like L3 schedule, Engineering Progress and Performance report (EPPR) , Short term work plan (STWP) and Trends
• Technical Specification preparation/review, Bid Evaluation and Drawing/Calculations review for Steam and Water Analysis System (SWAS), PTC 6 Flow Nozzles, Venturis and Low Loss Flow Tubes, Control Valves, Pressure regulators, Back pressure regulators, Orifice plates, Metal Seated ON/OFF valves and Temp/Flow/Level and Pressure Instruments.
• Co-ordination for C&I Portion of Mechanical Packages and Guidance in Preparations of I/O List, Instrument Indexes, IID’s, Level setting diagrams.
• Review of P&ID’s & System descriptions.
• Preparation of DCS Marcos (Siemens T3000) and Review of OLCS logics.
British Petroleum West Nile Delta Onshore Gas Plant – FEED (Aug – Oct 2012)
• Preparation of MTOs of Control Valves, ON/OFF Valves, SIS Valves, Motorized Valves, Rupture Disks, Restriction Orifices ,Ultrasonic flow Meters, Vortex Flow Meters, Magnetic Flow Meters.
• Preparation of PAS I/O MTO and SIS I/O MTO
• Preparation of Cable MTO and Branch Cable Tray MTO for PAS, SIS and FGS.
• Checking of MTOs for Pressure, Differential Pressure and Flow Transmitters

LANCO Infratech Limited
Manager(C&I).

   Mar 2010
— Aug 2012

2 x 366 MW Lanco Kondapalli Stage III CCPP (Functional Position – Project Lead)
• Responsible for Engineering progress, cost performance, site support and Engineering quality.
• Responsible for complete Coordination with other engineering departments, Project Management Group, procurement, Site, Customer and Engineering management.
• Resolution of commissioning related issues and customer punch points for Kondapalli Stage II CCPP project including On-site logic changes in the Main Plant DCS – ABB (Symphony Harmony).
• Coordination with engineering consultant (TPSC). Tracking and approving progress reports for consultant payments against milestones.
• Technical Specification preparation and Bid-evaluations of Main Plant DCS (Honeywell EPKS), Gas Metering system for Custody transfer(Emerson – Daniel) , PLC, Field instruments, Erection package and C&I portions for various BTG & BOP Mechanical packages like Steam Turbine, HRSG, CAS, and STG Lub Oil purification system.
• Review and finalization of P&ID’s, process descriptions and control philosophies.
• Detail Engineering of Steam Turbine Package (DEH –ABB Symphony Harmony, ETS - Siemens S7 PLC, TSI – Bentley Nevada), Main Plant DCS (Honeywell EPKS), Field instruments and Gas Metering system etc.
• Review and finalization of DCS Macros, OLCS & CLCS.
• Review & finalization of I/O List, Instrument List, Cable schedule and interconnections.
• Hardware & Software FAT for Main Plant DCS, TSI & ETS of Steam Turbine, Simple Cycle PLC system and Gas Metering System.
• Visited project site 8 times at different stages of the project.
2 X 600 MW Phase I Anuppur Coal based Thermal Power Project (Functional Position – Dy. Project Lead)
• Coordination with other engineering departments, Project Management Group and Customer.
• Finalization of engineering consultant for detail engineering work.
• Participation in Technical review meeting and Project review meeting.
• Review and finalisation of instrumentation in P&ID’s, process write-ups and control philosophies.
• Detail Engineering of Main Plant DCS (Emerson Ovation) and Vibration monitoring system (VMS)
• Detail Engineering of Steam Turbine package.
• Review & finalization of I/O List, Instrument list, Cable schedule and interconnections.
Steam Turbine Package for Solar Thermal Power Project.
• Bid Evaluation of Steam Turbine Package (Siemens/Alstom).

ALSTOM
Lead Engineer(C&I).

   Jun 2007
— Mar 2010

Contract Engineering.
• Responsible for co-ordination with project management, procurement, lead design center and site.
• Review of detail engineering documents like instrument list, Electrical consumer list, signal exchange list, Electrical connection diagrams, instrument location drawings, cable tray layout etc.
• Review of P&IDs, logic diagrams, I/O List, Operation Procedures, Control Philosophies, Cabling quantities and Cable tray BOM.
• Responsible for Specification preparation, bid evaluation and detail engineering of field instruments, cables & Heat tracing package.
• Visited Utran project site twice at different stages of the project.
Projects -- Flevo/FOS/TERGA / Skopje CCPP, Utran.

Proposal Engineering.
• Raising Bid clarifications, preparation of BOM and participation in cost estimation.
• Technical discussion and scope finalization with the package suppliers.
• Review of technical offers for DCS (ABB Symphony Harmony & ALSTOM ALSPA), BMS, Auxiliary packages and special instruments.
• Co-ordination with the process groups and preparation of tender write-up
Proposals 2 x 250 MW NTPC Bongaigaon Project, HRSG for CCPP Projects (Hassyan / Gebze / Dhuvaran III / Hatay)

BHARAT HEAVY ELECTRICALS LIMITED (BHEL)
Sr. Engineer(C&I)

   Jan 2000
— Jun 2007

Contract Engineering
• Discussion and Co-ordination with Customer, Customer’s consultant, Vendors, Other engineering
Disciplines and Manufacturing units.
• Review and finalization of P&ID’s and Control philosophies.
• Preparation of Drive Control Philosophies, Design Memoranda’s and control room layout.
• Preparation of Drive-Lists, I/O Lists, ALARM Schedules & SOE Schedules for different projects.
• Preparation of OLCS/CLCS Schemes (PA/FD/ID Fan’s / BFP / CW / ACW / AIR-HEATER /Boiler
Emergency cool down / FBHE blowers/ SEAL pot blowers / HPBP / APRDS / Analog Control Schemes
(ACS) etc.) for different Projects based on Coal-fired & CFBC Boilers.
• Technical Specification preparation and Bid-evaluations of C&I portions for various Mechanical
Packages.
• Preparation of technical specifications and bid evaluations for Control valves, Field instruments and PLC
Panels.
• Detail engineering of PLCs, Control valves and field instruments.
• Preparation of cable schedules and interconnections.
• Review of Data sheets and wiring diagrams of HT, LT & Bidirectional electrical drives.
• Review of piping isometrics for Instrument interfaces.
• Participation in DCS FAT (MAX DNA).
• Visited Surat lignite project site during detail engineering
Projects:
Coal Based Power Plants: BELLARY (1 X 500 MW), PARICHHA (2 X 210MW), and JINDAL-RAIGARH (4 X 250 MW).
Lignite/Limestone based power plants with CFBC Boiler: SURAT-LIGNITE (2 X 125MW), NEYVELLI (2 x 250MW) and BARSINGHSAR (2 x 125MW).

Proposal Engineering
• Raising Bid clarifications, Discussion with Customers and internal discussion with Units/Dep’t,
• Preparing BOM for Station C&I, Cable estimates and Cost estimates for control valves & flow elements
• Review and finalization of Proposal P&IDs, Schedule of deviations and tender write-up.
Proposals: JSW - JAIGAD 4 X 270MW TPS, JSPL - RAIGARH: 2 X 150MW & ANGUL: 8 X 150 MW TPS (CFBC Boiler), 2 X 100MW (Net Power) BANJARSARI MINEMOUTH POWER PLANT (INDONESIA).