Summary

I am a highly skilled and experienced MEP Engineer with more than 9+ years of job experience in construction field. I have undergone rigorous training to enhance my expertise. I am confident that you will find me as an apt candidate to obtain this job, and I shall give my best towards the job and the company.

My project execution and management skills are excellent and I enjoy working as part of a team, as well as liaising with consultant and client. I enjoy the company and support of my peers while being able to manage my priorities and work. My day-to-day job involves efficiently managing others, communicating complex data to the technical team and breaking down this information for consultant and clients.

Problem-solving and troubleshooting are tasks which I face on a daily basis and am confident at resolving. When there is an issue, as often happens in large-scale projects, I am sure to investigate the issue fully, scope out the best methods to resolve it, probe implications of each method, and communicate the data clearly with all relevant team members.

Education

Al Falah university
Mtech (Electrical)

   Jul 2014
— Jul 2016

Aligarh Muslim University
Bachelor of Engineering (Electrical)

   Jul 2004
— Jul 2008

Aligarh Muslim University
Diploma in Engineering (Electrical)

   Jul 1999
— Aug 2002

Experience

colliers International
Assistant Manager

   Oct 2015
— Feb 2018

Supervision of all MEP Related Godrej Icon & Godrej Oasis at sec-88A,Gurgaon,having 15 Nos.of High rise towers (G+31,G+17,G+13,G+11,G+9).
Coordination between MEP works and all other disciplines including Drawings,Specifications,Contracts and Execution.
Study the Drawings & specifications and if required raise request for information/clearance (RFI)
Incorporate MEP Drawing revisions & changes into the construction activities/program.Notify variation/claim as applicable.
Review MEP contractors submissions including Shop drawings,Material submittal etc.
Coordination with Consultants,Client,Contractors etc.Follow up on approvals & NOCs.
Study the program of works and updates.Follow the progress of MEP contractor.
Ensure on time delivery of MEP material and equipments;long lead items
Supervision of MEP subcontractor works for technical,Quality,Safety & Progress issues.
Regularly attending progress review meeting with vendors for capturing any discrepancy between planned and actual progress
Arrange MEP clearance for Civil works.
Certify MEP contractors Bills.Review all correspondence from MEP contractor and verify their claims.
Ensure Project handing over as per the project requirements,Snagging,De-snagging.cleaning etc for MEP works.
Manage the submission of MEP project closeout documents;As Built Drawings,O&M Manuals,commissioning Reports spares etc.
Ensure Safety & Welfare of the work force.Ensure proper and safe work place,proper & egress,suitable PPE ensurance for contractors staff.

Piyush group
Assistant Manager

   Feb 2014
— Sep 2015

Supervision of all MEP activities at Piyush Horizon at sec-1,Dharuhera spread over 8 acres of land, having 8 Nos.of High rise towers (G+15).
Execution, testing and commissioning of 2 nos of 500 kVA transformers,2 nos of 3 Panel HT VCB board,2 nos of 125kVA DG sets, Compound Lighting, Internal electrification of flats for load @ 8 kW for 2 BHK & @ 16 kW for 3 BHK.
Installation, commissioning and testing of 140 KLD Plumbing system with WTP (MGF & ACF Filteration) system, Rain water harvesting system.
Installation Commissioning & Testing of 450 KLD STP.
Installation, commissioning and testing of Fire Fighting system which includes 200 KLD fire tank with 1 no. of Diesel engine, 1 no. 100 HP main fire pump,1 no.100 HP Sprinkler pump & 1 no.7.5 HP Jockey pump.
Installation, Commissioning & testing of Conventional type Fire Alarm System including MCP, Hooters and optical smoke detectors.
Installation, Commissioning & testing of Basement ventilation system including hanging of GI ducts, installation of Axial flow fans for exhaust and fresh air requirement.
Installation, commissioning and testing of 2 Nos of Lifts having capacities of 13 persons.

Vatika group
Senior Executive

   Jun 2012
— Feb 2014

A project of 750 acres township Vatika India Next,Sector-83,Gurgaon,with 8 Nos of Mid rise towers (G+8) and 7 Nos of Low rise towers (G+3).
Internal electrification of 1,2,3 & 4 BHK, Penthouse, Slab Conduiting & Surface Conduiting,Wiring,switchgear fixing etc.
Installation of Generators (2 nos.500 KVA & 2 no. 625 KVA)
Installation,Testing and commissioning of HT Panel, Main LT Panel,MDBs SDB
Electrification of street pole light, Feeder Pillar & cable laying work.
Installation, commissioning and testing of internal Plumbing work
Installation, commissioning and testing of External Plumbing work including sewerage, rain water harvesting system.
Installation, commissioning and testing of Fire Fighting system, ventilation system of basement including hanging of ducts, installation of fans etc.
Installation, commissioning and testing of Vertical transportation system i.e. Lifts

JRC Grid Engineers Pvt.ltd
Electrical engineer

   Aug 2008
— May 2012

Construction of Residential Accommodation for Army Welfare Housing Organization at Greater Noida,Phase III
Internal electrification of 2,3 & 4 Bedroom, Penthouse, and L.T. Panel Slab Conduiting & Surface Conduiting.
Electrification of street pole light & cable laying work.
To provide the entire electrical solutions as per requirement..
Review Inspection and Test Plans in order to perform all required inspections and witnessing all required tests and add witness and hold points for the Client’s Inspection.
Review inspection reports and records of Quality Control carried out on completed and running Project activities.
Review Client’s Inspectors deliverables, analyse and resolve issues and problems emerging during the Quality Control activities. Ensure that all inspection and tests witnessed by clients
Checking the Workmanship and material Quality as per approved make and standard work for the Right quality and standard work
Daily & Weekly work Progress Report Preparation and Keep the Record
Preparing the Monthly work Progress Report for Claim with Measurements
Daily conduct and maintain the tools box meeting and checking the Height work Permit (above 2m)
Preparation of Project Report for correct and Timely information for the Progress of work
Responsible for Highlighting foreseen Problem & Delays in advance Escalating to the PM
Weekly Material Requirement to be send by email to office
Conduct site visit and collect information required for tie-in projects with existing facility and expansion project