Senior electrical engineer in O&G, Consult PM in T&D


Last Updated: 27th July 2019 (over 3 years ago)

Address
Czech Republic

E-mail
Locked

Phone Number
Locked

Gender
Male

Age Range
45 to 54

Qualification Level
Masters

Languages
Czech, English, Russian, Slovak

Summary

Project management and consultancy on , power transmission and distribution (T&D) projects.

Consultancy as Project manager and Senior electrical engineer. Prequalification of companies, tender documentation preparation, tender coordination and evaluation and final contract preparation and coordination.
Technical specifications review and engineering on Power and T&D projects.

Electrical engineering in Oil and Gas (O&G) on EPC projects, analyses of power distribution grids, FEED design of power distribution and power generation systems, detail design of power distribution in hazardous and non hazardous areas, technical coordination of subcontractors and procurement, site supervision, commissioning, leading of electrical teams, estimation, scheduling and work coordination on the projects.

Education

Technical University, Faculty of Electrical Engineering
University diploma electrical engineer (Master of Science in EE)

   Sep 1983
— Jun 1988

Experience

GOPA Intec GmbH (Germany/Nigeria)
Project Manager consultant

   Jun 2012
— Current

Lot 5 Consists of three Projects. Erection of two substations 132/33kV and extension of another two substations, erection of two Transmision lines 132kV, Erection of 330/132kV substation and erection of GIS 132kV substation.
Location: Nigeria, Client: NDPHC
Main project features: Erection of 330/132kV and 132/33kV substations in Asaba, Benin, Agbor and Nkalagu, erection of 132kV DC lines Agbor Asaba and Ihial Orlu. Addition of transformers 132/33kV to two substations with switchyard and control room modifications in Nkalagu and benin. Erection of 132/33kV substation in Orlu.
Activities performed: Complete management of the project, engineering and commercial part control. Documentation review, site survey, progress reports control, problems solving coordination, invoicing review and approving etc.

Lot 7 Consists of three projects. Erection of two substations 330/132kV, Transmission lines 330 and 132kV and Extension of three substations 132/33kV by addition of one new transformer.
Location: Nigeria, Client: PHCN (TCN)
Main project features: Erection of 330/132kV and 132/33kV substation in Kainji lake region, erection of 330kV line crossing the river. Erection 132kV DC line btw substations. Addition of transformer 132/33kV to three substations with switchyard and control room modifications.
Activities performed: Documentation review, site survey, progress reports control, problems solving coordination etc.

GOPA Intec GmbH (Germany/Nigeria)
Project Manager consultant

   Jun 2012
— Current

Lot 5 Consists of three Projects. Erection of two substations 132/33kV and extension of another two substations, erection of two Transmision lines 132kV, Erection of 330/132kV substation and erection of GIS 132kV substation.
Location: Nigeria, Client: NDPHC
Main project features: Erection of 330/132kV and 132/33kV substations in Asaba, Benin, Agbor and Nkalagu, erection of 132kV DC lines Agbor Asaba and Ihial Orlu. Addition of transformers 132/33kV to two substations with switchyard and control room modifications in Nkalagu and benin. Erection of 132/33kV substation in Orlu.
Activities performed: Complete management of the project, engineering and commercial part control. Documentation review, site survey, progress reports control, problems solving coordination, invoicing review and approving etc.

Lot 7 Consists of three projects. Erection of two substations 330/132kV, Transmission lines 330 and 132kV and Extension of three substations 132/33kV by addition of one new transformer.
Location: Nigeria, Client: PHCN (TCN)
Main project features: Erection of 330/132kV and 132/33kV substation in Kainji lake region, erection of 330kV line crossing the river. Erection 132kV DC line btw substations. Addition of transformer 132/33kV to three substations with switchyard and control room modifications.
Activities performed: Documentation review, site survey, progress reports control, problems solving coordination etc.

GOPA DECON International (Germany/UAE)
Resident engineer

   Sep 2010
— Jun 2012

Project scope includes primary power distribution station 132/22kV and ring substations 22kV, feeder pillars, service cabinets cable routing. The project consultancy and supervision was done on behalf of Abu Dhabi Distribution Company. Position as Resident Engineer approved by ADDC.

Fichtner Consult Engineers (Germany/UAE)
Senior electrical engineer

   Sep 2009
— Aug 2010

Yemen Transmission Backbone project
Project scope includes increasing of transfer capability and renovation of Yemen national grid. In scope is also erection of new transmission lines and new transmission substations
The main scope was prequalification of companies, prequalification report preparation, tender documentation finalization and preparation for future bidders.

Extension of 400kV substation Marib2 (Yemen)
Project scope includes enlargement of existing 400kV substation and connection of the new substation part to the existing substation and also to new part of existing power station Marib.
In the scope were technical and commercial bid evaluation, bid evaluation report preparation and final contractor recommendation.

Extension of power station – Marib2nd (Yemen)
Project scope includes extension of existing power station Marib with the new part Marib 2 including new turbine-generators separated control system and interface to the outdoor 400kV substation.
Project scope includes technical bid evaluation of bids,

Sur grid station (Oman)-tender site visit.
Project scope includes erection of new substation132 kV and renovation of the existing 132kV substation. In the scope was also erection of over head line – double circuit from the new substation to the city Ayjah.
In the scope were site survey and preparation of documentation for tender preparation.

Feasibility study of elimination of 33kVlevel in the Takreer refinery substation (UAE)
Project scope includes elimination of existing 33kV switchgear. In relation to this matter is feasibility study of the planned change.
In scope are included site survey in the substation and related sites and the Site survey report preparation. Feasibility assessment report preparation.

Four cities project (Yemen).
Project scope includes renovation of distribution grid 132kV/33kV/11kV, renovation of old substation and erection of new substations of distribution grid in main Yemen cities. In the cities Sana’, Aden, Taiz, Hodeidah will be also erected new overhead lines and cable connections among the related station.
In the scope were site survey of 90 substations and preparation of site survey report. The site survey report will be as base for conceptual design preparation.

Fluor Brno (CZ) O&G
Senior electrical engineer

   Jun 2006
— Aug 2009

Damage report assessment Mazheikai refinery (Lithuania),
Working as a Lead engineer responsible for price estimation of rebuilt, material list preparation, site survey and client negotiations. All work done in co-operation with Fluor Haarlem (NL).

IGCC project Gdansk.
FEED package preparation. HV, LV power distribution basic design in cooperation with Fluor Haarlem.

The Programme 10+. Renovation of LOTOS Refinery in Gdansk (Poland)
Working as an Area electrical lead engineer on the EPC project. Large part of project was HV/MV/LV power distribution of refinery renovation. Scope of activities: New GIS switchgear 110kV installation, modification and rerouting of overhead lines, new HV/MV stations and power distribution erection, power supply of existing and new process units, erection and modification of new and existing process units, renovation of fire alarm system and telecommunication grid in the refinery, detail design documentation preparation and co-ordination, preparation of contractual documentation, engineering co-ordination of contracts, site supervision and technical co-ordination with the client.

ABB Lummus Global Brno (CZ))
Electrical lead engineer

   Apr 1997
— May 2006

Work on various projects like Nizhnekamsk (Russia), new cracking heater in the ethylene plant. Work done in co-operation with ABB LHT Hague. Scope of the work : procurement, design and engineering of electrical parts including new substation.

Compressor station Korpedje (Turkmenistan)
Cooperation with MAN FIA (Germany). Detail design preparation, engineering, one year site supervision, commissioning and start up of electrical power distribution system. El. part included HV, LV power distribution, 6kV power generator, UPS’s, black start diesel generator and 36kV back up supply from overhead line , SCADA control system etc. All work done in co-operation with a multicultural team.

Ethylbenzene II in Kaucuk Kralupy (CZ)
Position as a Lead engineer. Scope of work : Detail design preparation, procurement and engineering, including technical negotiations with vendors and with the client, HV and LV power distribution with substation design. (Project according to DEP standards.)

Amerya Alexandria (Egypt)
Detail design, procurement and engineering, one year site supervision, commissioning and start up of electrical power distribution system. El. part consisted of HV/LV distribution, substation, UPS’s, diesel generator, etc. Work done in multicultural team with international technical co-operation.

Styrene III in Kaucuk Kralupy (CZ)
Participation in detail design as electrical engineer (design, engineering and procurement) (Project according to DEP standards.)

FCC-OSBL in Kaucuk Kralupy (CZ)
Participation in detail design as electrical engineer (design, engineering and procurement) (Project according to DEP standards.)

TUPRAS Izmir refinery (Turkey)
Proposal as FEED package, design and engineering, including HV/LV power distribution with main new substation and some small substations in the refinery.

ABB Energo / PGS Brno (CZ)
Electrical project engineer

   Mar 1994
— Mar 1997

Power distribution and generation
Electrical project engineer
Engineering and coordination of power generation and distribution plants.

Aktjubinsk (Kazachstan)
Boiler and TG room design and delivery, including engineering and co-ordination. Work done in co-operation with ABB Mannheim.

T-G room reconstruction in Kaucuk Kralupy.
Engineering and site supervision of erection.

Reconstruction of power plant Melnik III
Engineering and site supervision of erection.

Another small projects including engineering and coordination of el. parts.

VUES Brno (CZ)
Design engineer

   Sep 1988
— Feb 1994

Manufacturing company for electrical rotating machines
Design of electrical machines and special electrical drives for miscellaneous purposes.