Project Management, Engineer I, Superintendent


Last Updated: 26th June 2018 (over 4 years ago)

Address
Jordan

E-mail
Locked

Phone Number
Locked

Gender
Male

Age Range
55 to 64

Qualification Level
Degree

Languages
Arabic, English

Summary

Engineer I, Site Superintendent, Site manager
Commitment, Decision maker, extensive follow-up for activities and plans, Teamwork lover
I am with the "Three Cs of Success: Collaborate, Coordinate & Communicate".
Saudi ARAMCO GROUP EXPERIENCE/Kingdom of Saudi Arabia (Through Al-Hoty Company), (SAUDI ARAMCO ID: 7106712)
PROJECTS:
a. Location: BI-28-10012 - HOME OWNERSHIP LOTS DEV. AT JUBAIL
b. Location: NORTH PARK OFFICE COMPLEX, DHAHRAN
c. Location: NUAYYIM ASL CRUDE INCREMENT 100 MBCD PROJECT, NUAYYIM
d. Location: HARADH GAS GATHERING & CRUDE PIPELINES INCREMENT III (BI-3177), HARADH
e. Location: ZAMEL AND TURBAG ENGINEERING DESIGN OFFICE, ALKHOBAR
f. Location: HARADH GAS GATHERING & CRUDE PIPELINES (JO: 31421), HARADH AL CRUDE INCREMENT II (JO: 82552) & HAWIYAH CENTRAL WIP (Under JO: 82551), HARADH
Previous Duties and Responsibilities
 Design Coordinator
 Manage the design from concept to final design,
 SAPMT Site Representative
 Supervise the works on site,
 Ensure the implementation of the applicable safety standards,
 Ensure project quality is implemented,
 Manage the day to day construction activities,
 Review and approve project schedule,
 Supervise the consultant and Contractor activities,
 Participate to the progress meetings,
 Evaluate the construction progress and advise on actions to be taken to keep the project under control,
 Provide the required technical support to overcome the construction issues
 Report to SAUDI ARAMCO Project Engineer the performance of the project,
 Coordinate with Royal Commission and other services providers for required approvals and hand over requirements,
 Review and follow the construction schedule,
 Adjust design as required to ease future maintenance of facilities
 Adjust resources level to ensure the respect of the project schedule,
Consolidated Contractors Company (C.C.C.)
PROJECTS:
a. Location: YANPET Expansion Ethylene Facilities (YEEF), Yanbu
b. Location: PTA Ibn Rushd, Yanbu
c. Location: Samad 2 - Ethul Hexanol Plant (S2EH)/ Jubail
d. Location: Petrokemya CSA 1 & CSA 3, Jubail
e. Location: Pemref Olefin Upgrading, Yanbu
f. Location: Cristal Pigment Plant, Yanbu
g. Location: South Medinah Water Reservoirs, Medinah
Previous Duties and Responsibilities

 Ensure the implementation of the applicable safety standards,
 Ensure project quality is implemented,
 Manage the day to day construction activities,
 Adjust resources level to ensure the respect of the project schedule,
 Supervise the Civil work: of casting foundations, pipe racks, platforms, paving & asphalts,
 Supervise the Erection of steel structures, pipe supports & platforms,
 Coordinate all concrete mixes and ensured that materials were within specifications.
 Maintained correspondence with Clients,
 Ensure to get the client approval of all materials.
 Supervise the construction of reinforced concrete foundations for heavy equipment, U/G concrete structures and pipe rack foundations, structural steel erection, service buildings including H.V.A.C. and electrical works, U/G piping and roads,
 Supervise temporary works include dewatering and sheet piling,
 Supervise all civil works and painting

Education

King Fahad for Petroleum and Minerals / Dhahran, Saudi Arabia.
Bachelor of Civil Engineer

   Sep 1981
— May 1986

Civil Engineering

Experience

Saudi Aramco (Through Al Hoty Company Sponsorship)
Engineer I, Saudi Aramco Project Management Team, Site Superintendent

   Mar 2002
— May 2013

2011 – 2013 Home Homeownership Lots – Jubail project
• Phase I: Construction of Infrastructures and 494 villas
• Area of 1,5 hectares
• Project Cost: USD 144 Million

BI-28-10012 provides for the Home Ownership Lot Development,
Phase I, at Al-Mutrafiah, Jubail Industrial City in the Eastern
Province of the Kingdom of Saudi Arabia, per the approved
Preliminary Scoping Paper (PSP). Under this project, Home
Ownership (H/O) Lot Development will be carried out in Two
(2) Phases namely Phase I and Phase II.

Al-Mutrafiah, the project site (Phase I & II) will be developed
to accommodate construction of 838 housing lots. Phase – I
will accommodate 494, in total, varying lot sizes for housing units
for sectors F1-1, F1-2 and F1-3 and in addition, three (3) local
Day mosques. Out of which, a total of 344 housing units will
be constructed under Phase – II. Phase – I, shall be constructed
in Two (2) Stages namely Initial & Final site development.
My role was as follows:
Engineer I, Site Superintendent
 Managed design of all infrastructures with designers to final documents (IFC),
 Coordinated with all services providers including Royal Commission, SEC and MARAFIQ for formal approval of IFC,
 Preparation of all contract documents for Initial and Final Site development Contracts, as well as the PMC (Consultant) Contract
 Supported the bids evaluation and awarding of contracts

SAPMTSite Representative
 Managed the current two contracts:
First Contract for the Initial Site Development Contractor, and
Second Contract for the PMC (Consultant),
 Ensured the Safety the Project and Safety Requirements are implemented and adhered all the time as per the Safety Standards Requirements,
 Managed the day to day construction activities,
 Reviewed and approved project schedule,
 Managed the overall budget of the initial phase,
 Supervised the consultant activities,
 Participated to the progress meetings,
 Evaluatedthe construction progress and advise on actions to be taken to keep the project under control,
 Provided the required technical support to overcome the construction issues
 Reported to SAUDI ARAMCO Project Engineer the performance ofthe project,
 Coordinated with Royal Commission and other services providers for required approvals and hand over requirements,

2010 – 2011 North Park Office complex project
• Buildings (offices, supports services, parking, site and landscaping…)
• Project Cost: USD 365 Million.

My role was as follows:
SAPMT Site Representative
 Ensured the Safety the Project and Safety Requirements are implemented and adhered all the time as per the Safety Standards Requirements,
 Managed the day to day construction Civil activities for Solar system works in the Parking Lots,
 Supervised the works on site,
 Ensured the implementation of the applicable safety standards,
 Ensured project quality is implemented,
 Participated to the progress meetings,
 Implemented solutions to ensure the project stays on tracks
 Report to SAUDI ARAMCO the performance of the project,

2007 – 2010 Nuayyim ASL Crude Increment 100 MBCD project
• GOSP (Gas & Oil Speration Plant),
• Pump Station’s Stabilizer Upgrade,
• Pipelines approximately 450 Kms,
• Residential and Industrial Complex Expansion,
• Project Cost: USD 2 Billion.

The project covers construction of Gas and Oil Seperarator Plant (GOSP), Pump Station’s Stabilizer Upgrade, Pipelines (Approximately 450 Kms of 24”, 16”, 12” and 8” dia. Crude, sour gas and water lines), and Residential and Industrial Complex Expansion.
My role was performing the following:
SAPMT Site Representative
 Ensured the Safety the Project and Safety Requirements are implemented and adhered all the time as per the Safety Standards Requirements,
 Managed the overall budget of the Residential and Industrial Complex Expansion project,
 Reviewed and follow the construction schedule,
 Supervised the project activities for all disciplines (Civil, Mechanical, Electrical, HVAC), and ensure quality Assurance implementation,
 Provided the required technical support to overcome the construction issues,
 Adjusted design as required to ease future maintenance of facilities,
 Adjusted resources level to ensure the respect of the project schedule,

2004 – 2007 Haradh Gas Gathering & Crudes Pipelines Increment III project:

Complete construction of Crude and Gas Pipelines for approximately 164 KM. The project involves major Civil and Piping activities in addition to all mechanical works. Civil work involvement for casting foundations, full thrust anchor blocks, pipe racks, platforms, paving slabs, asphalt works, fencing,…etc. Erection of steel structures, pipe supports, platforms and miscellaneous steel erection works. Piping and mechanical works involve trenching, stringing, welding, lowering, backfilling and berming, and hydro testing of all pipelines. The project involves also 28 nos. of hot taps on existing pipe lines.

My role was as follows:
Site Superintendent
 Ensured the Safety the Project and Safety Requirements are implemented and adhered all the time as per the Safety Standards Requirements,
 Managed all site activities including Civil, Mechanical, and Electrical…
 Constructed 164 kmsof Pipeline,
 Supervised the Civil work: of casting foundations, pipe racks, platforms, paving & asphalts,
 Supervised the Erection of steel structures, pipe supports& platforms,
 SupervisedPiping and Mechanical works involve trenching, stringing, welding, lowering, backfilling and berming, andhydro testing of all pipelines,
 Supervised the hottaps activities on existing pipe lines,
 Managed the day to day construction activities,

2003 – 2004Zamel&Turbag Engineering design office project
• Design of the Harad crude pipeline, from the concept to the final / detail design,
• Design for the construction of Crude, Gas and Seawater Pipelines of approximately 300 KM.
Design stage for HARADH GAS GATHERING AND CRUDE PIPELINES INCREMENT III (BI-3177) AND SEAWATER PIPELINES INCREMENT III (PART OF BI-3176). The design period involved three stages: First stage the Project Proposal for the mentioned projects, which was finished within 8 weeks including site surveys and design of pipeline routes, design of all civil, mechanical, electrical,…works that are defined by the planning department of ARAMCO. The time limit was a challenge for all the team. The second stage was the detailed design for Administration Building involving all works to hand over the building. The third stage stage was the detailed design of the pipelines’ projects (after nominating the wining Contractor). Design for the construction of Crude, Gas and Seawater Pipelines of approximately 300 KM.
My role was as follows:
 Managed the design from concept to final design,
 Applied appropriate standard of design,
 Developed the schedule and manage assignment,
 Report progress to SAUDI ARAMCO Project Engineer.

2002 - 2003 HARADH GAS GATHERING & CRUDE PIPELINES (JO: 31421), HARADH AL CRUDE INCREMENT II (JO: 82552) & HAWIYAH CENTRAL WIP (Under JO: 82551), HARADH, SAUDI ARABIA.

Complete construction of Crude, Gas and Sea Water Pipelines for approximately 88 KM (JO: 31421) and 130 KM (JO: 82552). The projects involve around 600,000 M3 of rock excavation, verification and calculation of rock quantities. A major civil work involvement for casting foundations, full thrust anchor blocks, pipe racks, platforms, paving slabs, asphalt works, fencing,…etc. Erection of steel structures, pipe supports, platforms and miscellaneous steel erection works.
My role was as follows:
 Site Superintendent
 Ensured the Safety the Project and Safety Requirements are implemented and adhered all the time as per the Safety Standards Requirements,
 Managed all site activities including Civil, Mechanical, and Electrical…
 Construction of 200kms Pipeline,
 Supervised the Civil work: of casting foundations, pipe racks, platforms, paving & asphalts,
 Supervised the Erection of steel structures, pipe supports & platforms,
 Supervised Piping and Mechanical works involve trenching, stringing, welding, lowering, backfilling and berming, and hydro testing of all pipelines,
 Supervised the hot taps activities on existing pipe lines,
 Managed the day to day construction activities,

Consolidated Contractors Company (C.C.C.)
Section Engineer, Civil Site Manager

   Sep 1999
— Feb 2000

1989 – 2000 CCC (Consolidated Contractors Company)

1997 – 2000 YANPET Expansion Ethylene Facilities (YEEF)
• Client: Saudi Yanbu Petrochemical Co.
• Value: US$ 113 Million

Complete construction of Ethylene Facilities with a capacity of 760,000 MTA. Scope includes civil works, piping, steel and heavy equipment erection, painting, insulation plus electrical and instrumentation works.

Section Engineer Construction

 Ensured the Safety the Project and Safety Requirements are implemented and adhered all the time as per the Safety Standards Requirements,
 Managed the execution of all project Civil works,
 Ensured that materials were properly used,
 Controlled details and priorities of work,
 Coordinated workshop fabrication, welding, insulation, coating, erection, pipe wrapping,
 Excavation and placement of pipes, with laboratory testing.
 Coordinated all concrete mixes and ensured that materials were within specifications.
 Coordinated with the Quality Control staff work specifications for the approval of the Client.
 Maintained correspondence with Clients,
 Ensured to get the client approval of all materials.

1995 – 1997PTA Ibn Rushd, Yanbu.
• Client:Arabian Industrial Fibers Co. Ltd. (Ibn Rushd).
• J.V. Partner:Tecnimont S.P.A., Milan.
• CCC Contract Value : US$ 77 Million
Construction of a complete PTA plant including precommissioning and commissioning works. Main scope of works includes concrete foundations, piping, equipment erection, painting, insulation, electrical, instrumentation, etc.
My role involved the following:
Section Engineer
 AS ABOVE

2003 – 2004SAMAD 2 - EthulHexanol Plant (S2EH).

• Client: Saudi Davy/ Al Jubail Fertilizer Co. (SAMAD).
• Contract Value: US $ 45.4 Millions

Work scope includes the construction of 2-Ethyl Plant at SAMAD Fertilizer Plant (Jubail) which consists of the following :
 - Synthesis Gas Unit
 - Butyraldehyde Unit
 - 2-Ethylhexanol Unit
 - Offsite Facilities and Services
 - Two Compressor Houses
 - Control Building
 - Substation
 - Analyser House
 - Mosque
Plus all electrical, HVAC and instrumentation related works.
 The Port Facilities Package involves the complete engineering, detailed design, procurement of materials, construction and commissioning of the following :
 Carbon Steel Storage Tank (37m diam. X 18m high)
 6" Stainless Steel Transfer Line, 800 m
 12" Stainless Steel Loading Line, 3500m
 Installation of 3 no. Pumps, 1 no. 8" Loading Arm and 1 no. Drain Vessel
 Construction of an Electrical/Control Building and a Guard House
 Electrical and Instrumentation works including DOC System

My role involved the following:
Section Engineer
 AS ABOVE

1993-1994 Area General Management, Riyadh Office.
Title Section Engineer Construction
Duties: As above

1992-1993 Petrokemya CSA 1 & CSA 3, Jubail.
• Client: Arabian Petrochemical Co. (PETRO-KEMYA).
• Consultant: Mitsui Engineering & Ship-building Arabia Ltd. (MESAR).
• Contract Value: US$ 35.7 Million.

Reinforced concrete foundations for heavy equipment, U/G concrete structures and pipe rack foundations, structural steel erection, service buildings including H.V.A.C. and electrical works, U/G piping and roads. Temporary works include dewatering and sheetpiling.

Site Engineer
 Supervised the construction of reinforced concrete foundations for heavy equipment, U/G concrete structures and pipe rack foundations, structural steel erection, service buildings including H.V.A.C. and electrical works, U/G piping and roads,
 Supervised temporary works include dewatering and sheet piling,
 Supervised all civil works and painting,
 Technical backup to the section
 Reviewed and interpreted drawings and prepared detailed sketches,
 Prepared calculations, checked quality against specifications and quantity of work,
 Revised all material submittals and ensure the use of approve materials,
 Report progress to management,
 Provided technical solutions to construction activities,
 Prepared quantities take off.

1991-1992 Pemref Olefin Upgrading, Yanbu.

• Client: PEMREF/J.G.C.
• Contract Value: US$ 11.3 Million.

Construction of all civil work and the instal¬lation of all the equipment for the plants:
Debottlenecking of F.C.C. Unit No.41, U.S.G.P. Unit No.62 and H.F. Alkylation Unit. Installation of C3/C4 splitter, a M.T.B.E. Unit, Alkylation and Feed Hydration, Hot Oil Process Station and Satellite House. Construction of all related utilities.

Site Engineer
 AS ABOVE

1989-1991 Cristal Pigment, Mechanical Works, Yanbu.
• Client: The National Titanium Dioxide Ltd. (Cristal)/Saudi Arabian Bechtel Co.
• Consultant: Saudi Arabian Bechtel Co.
• Contract Value : US$ 8.5 Million
Fabrication and Installation of approx. 750 tons of piping with average 4” dia.; erection of prefabricated structural steel, installation of 950 nos. of equipment ; in addition to refractory lining of 18 nos. of equipment (reactors and furnaces).

Title: Civil Engineer.
Duties:
Worked as a technical backup to the section (interpreted drawings and prepared detailed sketches, calculations, checked quality against specifications and quantity of work).

February 1989 - November 1989: South Medinah Water Reservoirs, Medinah.
• Client: Medinah Water & Sewage Authority.
• Contract Value: US$ 14.7 Million.

Title: Junior Engineer (Civil).
Duties:
Shared, in association with the Engineer In Charge, in the supervision of concrete placing, shuttering, steel fixing, back filling and earthworks.