Summary

• 23+ years’ successful experience, multi skills including 8 years as mid-level manager with 5 Multi-national Companies
• Ability to take decision & responsibility, presentation, write procedure, technical report and can work independently
• Professional experiences with Gas Turbines (M701F, 13E2, F9E, V94.2), STs, HRSGs OPS, MI, HGPI & CI
• Used to work with SAP, DCS, Historian, PI & PI Process Book, Eta-PRO, Thermo-Lyse, D7i, SAP90, AutoCAD
• Rewarded as a Professional Engineer & qualified for Control Room Engineer, PBE, BOPE and high voltage operation
• Erected & commissioned two Combined Cycle Power Plant as Owner engineer with min. variation order in time
• Worked with EPC (Hyundai Engineering & Construction Co) for 4.8 km bridge construction & gas pipe installation
• Conducted 218 trips RCA (Root Cause Analysis) to improved plant reliability, availability and reduced forced outage
• Monitored Performance of Gas Turbine, Steam Turbine, Condenser & HRSG as per ASME PTC 4.4
• Planed, measured, analyzed, presented to management for approval and continually improve Power Plant O &M
• Verified and endorsed monthly fuel gas & energy bills, faced technical audits and responsible for technical docs
• Coordinated with OEMs, Suppliers, Vendors & Contractors and conducted feasibility study and preparation MFS
• Familiar with Codes & Standards (NFPA850, ASME B31.1 & 31.3, ANSI, BS, API 650, EPRI, VGB, etc.)

Education

University of Dhaka
MBA (Finance)

   Feb 2005
— Nov 2007

Bangladesh University of Engineering & Technology (BUET)
B. Sc Engineering (Mechanical)

   Aug 1988
— Dec 1993

Experience

CNG (Haripur Power Ltd)
Maintenance Manager (Mechanical, Electrical, Instrumentation & Control)

   May 2018
— Current

Maintenance of 360 MW Combined Cycle Power Plant

Energypac Power Ltd
General Manager, Project Management

   Dec 2017
— Apr 2018

• Liaison with Client, and Lead Partner for approval of drawings, and procedures
• Make decision for all technical issues, advise to top management regarding critical issue
• Comply with Contracts, Codes & Standards, and local law
• Represent Energypac with other stake holders
• Coordinate with Supply Chain, design team, and HR
• Reduce wastage and save project cost
• Ensure work quality, site safety & security
• Complete the project activities as earliest possible time
• Prepare response for all Client and Lead partner queries, reports, mitigation plan, PTS
• Update project progress to Client, IKL, and top management
• Prepare RFI, material & employee requisition
• Adjust resources (tools, manpower, and logistics)
• Conduct daily, weekly, and monthly progress meetings
• Select vendor for different discipline (Civil, Mechanical, Electrical, and Instrumentation)
• Control sub-contractor to meet project commitment (quality, safety, and schedule)
• Managing project risks, and project administration

EMAL -Emirates Global Aluminum (EGA)
Engineer 1 (Process Efficiency & System Planning)

   Jan 2017
— Apr 2017

Monitor & improve plant performance, condition monitoring and improve reliability, perform perf test, maintain KPI, FDM, track budget and prepare generation & efficiency report

Emirates Global Aluminium ("EGA")
Lead Engineer (Asset Management)

   Dec 2011
— Dec 2016

• Support VP to manage assets, minimize energy losses and improvement plans for Power & Desal O&M
• Improve reliability & availability by conducting GTs, STs & HRSGs trips quarterly to Senior Management
• Solve technical issues by conducting technical meeting and communication with OEMs, User groups, Vendors
• Reduce FAC risk of 23 HRSG by developed and implement flow accelerated corrosion (FAC) management system
• Ensure compliance to OEMs by developing OEM advisories (TILs + CIBs) management and tracking register
• Developed & coordinate lube oil conditions monitoring, critical spares, and steam trap management for DUBAL
• Meet yearly KPI by reviewing asset performance targets, monitors and reports performance against plans
• Prepare ad-hoc RCA for repeated failures and generate ideas for improvement & develop new procedures
• Conduct feasibility study and preparation MFS of all new projects and repair/replace decisions on failed plants

Meghnaghat Power Ltd. and Haripur Power Ltd, IPP
Engineering Manager

   Jun 2007
— Dec 2011

• Prepared budget, challenging KPI to maximize profit and tracking Asset Management Optimization Program
• Improved plant heat rate by monitored the Plant performance and carried out RCA on all trips, forced outages
• Planed, developed and implemented effective equipment maintenance programs to maximize eqp. reliability
• Performed yearly capacity test, ensured compliance of PPA, GSA & LTSA, and prepared all external reports
• Verified and endorsed monthly fuel gas & energy bills, faced technical audits and managed HRSGs all type outages
• Was responsible for all Modification / Expansion / Development of the facility and the study for the modifications
• Maintained HRSG, condenser, piping, & QC for welding and prepared MFS, tendering, evaluation for major purchases
• Conducted/organized monthly internally technical training to share all lessons learnt for O & M personnel

Meghnaghat Power Limited and Haripur Power Limited, IPP
Control Room Engineer and Plant Engineer

   Dec 2002
— Jun 2007

• Operated 450 MW & 360 MW CCPP to high safe & environmental standards (OHSAS) at optimal efficiency
• Prepared shift, monthly operation report, maintain plant statistic and coordinated with Load Dispatch Centre
• Developed operation procedures like emergency responses, mock drill, contingency plan for ISO certificates
• Maintained boiler water chemistry and identified & solved problems, created punch list and warranty issues
• Met plant KPI, performed Start up and Shut down by APS, and involvement in the Plant Perf. Guarantee Test
• Issued PTW, isolated the system, participated in several Major, HGPI & CI outage and normalize the system
• Verified and accepted commissioning checklist, warranty issues, punch list items for most of plant items

AES Meghnaghat Limited and AES Haripur Private Limited, IPP
Lead Owner Project Engineer

   Jul 1999
— Nov 2002

• Completed two projects ahead of schedule with minimum variation order and within budgeted cost
• Complied World Bank Guidelines and OHSAS for HSE for worker and project affected people (PAP)
• Conducted daily, weekly & monthly progress meeting with EPC Contractors, Sub-contractors & Vendors
• Ensured the compliance of PPA, Supply Agreement, Master Specification, GSA and others EPC Contracts
• Verified mechanical completion and milestones payment, reviewed and approved mechanical & piping design
• Reviewed and approved all Method of Statements, NCR, DCR for all installation, ensured quality control
• Supervised the foundation, installation, erection of the mechanical equipment (701F GT, ST, HRSG)
• Qualified welders, visually inspection of TIG & Arc welding for pipe line; interpretation of RT
• Inspected underground piping, steel structure erection, civil foundation & buildings construction
• Witnessed all pump & turbine alignment, major lifting, pressure test for all piping system & pressure parts

Hyundai Engineering & Construction Co. Ltd
Mechanical Engineer

   Feb 1994
— Jul 1999

• Installation gas pipe along bridge & cross country, designed different type support and expansion loop
• Modeled steel structural and analyzed each component stress by SAP90 (Computer Program)
• Prepared all detail drawings for steel structure, lifting devices, piping, civil and site layout by AutoCAD
• Designed the lifting Elevator, Moving working platform, Setting carrier for Gas Pipe Line under bridge
• Estimated the material quantity, prepare the welding map & short piece location,
• Verified WPS & PQR, checked & qualified welder qualification test & inspected different NDT
• Inspected piping and steel structural welding and steel members fabrication as per AWS D1, 1-96
• Ensured quality control of access platform, different type of steel stair, pipe fitting and its welding
• Supervised structural detail of segment, Seismic device, bearing detail, Tendon Layout and Pier Head