Electrical and I&C commissioning engineer / supervisor
Last Updated: 11th June 2019 (over 3 years ago)
Summary
My name is Maxim Melnikov. I have a total of 11 years of full-time experience out of which 8 years on Lead/Senior level in EPC and Consultancy Companies for Oil & Gas and Mining in the Russia and Kazakhstan, including designing, construction, commissioning and project management positions for Electrical, Pipe Line, Solar and LV systems, holder of Master’s Degree in electrical engineering, confirmed by Canada World Education Services (#3976158) and by apostille.
Constriction, commissioning and start up: gas pipe line's equipment, compressors and gas transfer stations, gas turbine generator, steam turbine generator, substations, transformers, reactors, harmonic filters, diesel generators, switchgear and MCC, electrical part of processing equipment and HVAC, VSD , UPS, magnetic bearings system, heating system with heat tracing and Pentair skin effect equipment’s.
Electrical Engineering: Scope of Works Preparation, Conceptual design, FEED and detailed EPC design; specifications and data sheets; Cable sizing and Voltage drop calculation; Preparation of SLD; Equipment sizing calculation; Load schedules; HV/MV Substations designs; Generators, switchgears and power transformers; UPS, HV Overhead Power Lines; Variable speed drives; Lighting, Earthing and Lightning protection design, calculation & layout; Hazardous areas equipment selection; EASY PLANT ,Autodesk AutoCad, Compass, Microsoft Visio, Autodesk Naviswork, AVC smeta, DIALux, Power system design.
Education
Electrical and I&C commissioning engineer
Apr 2019
— May 2019
Master of technical sciences, specialty electricity
Sep 2014
— Jun 2016
Bachelor of Electric Power
Sep 2005
— Jul 2009
Experience
Electrical Superintendent
May 2019
— Current
Electrical and I&C commissioning engineer
Aug 2018
— Apr 2019
Schedule and plan preparation of commissioning related to Electrical based on the schedule of overall commissioning.
- Utilizing of EasyPlant software for better quality of Commissioning and Pre-Commissioning activities;
- To instruct the daily/weekly/monthly activity to Electrical Supervisors and workers;
- To carry out the pre-commissioning activity related to Electrical (e.g. support for motor uncoupled/coupled run test, function test, support/set-up of electrical equipment to commission, make readiness of electrical commissioning) in accordance with the pre-commissioning procedure;
- To participate in all the commissioning activities and subsequent day to day operation of the assigned plant;
- To carry out the start-up activities in accordance with the operating procedures.
- To carry out periodical tests and verification to ensure the process and safety equipment is in good working condition;
- To assists in troubleshooting and proposes changes to improve the safety and availability of the installations;
- To perform minor maintenance activities as per agreed procedures;
- To co-ordinate with Maintenance for electrical equipment functional checks.
Electrical and I&C commissioning supervisor
Jul 2017
— Aug 2018
Lead Electrical Engineer
Feb 2015
— Jun 2017
1) 2015-2016, customer KAZ Minerals PLC "Plant of solvent extraction and electrolysis, oxide ore and Aktogay deposit infrastructure", "Off-site mains and facilities of constant water supply of Aktogay mining and processing plant, pumping stations PS1, PS2, PS3",
2) 2016-2017 January, customer KAZ Minerals PLC “Aktogay Sulphide Plant”,
3) 2017 customer Doosan Heavy Industries LTD "National Industrial Petrochemical Technology Park” in the Atyrau Region (Karabatan and Tengiz Fields) Gas turbine power plant 310MW " .
Development of new design solutions with necessary drawings (AutoCad and Compass) and calculations, introduction of changes and coordination with the customer. Installation and commissioning of: substations equipment 10kV and 35кV, pipeline equipment, gas transfer stations, transformers 110/35/10kV ABB, 110/10kV Hyundai, 10kV ABB reactors, 10kV harmonic filters, VESDA system, diesel generators Perkins and PatTech,10kV and 0.4 kV switchgear and MCC, electrical part of processing equipment and HVAC, VSD ABB ACS 550/800/2000 and Siemens Sinamics, UPS Schneider Electric, Siemens SGT800 gas turbine generator, Doosan Skoda Power MTD 30 CA-HP steam turbine generator. Controlling a purchase, delivery and acceptance of equipment, maintaining reports and write-offs. Preparing cost estimate documentation in AVC SMETA. Organizing installation and commissioning works according to customer requirements, LockOut-TagOut system, rules and regulations of the Republic of Kazakhstan and the Russian Federation. Installation of electrical equipment in hazardous areas (Ex). Work with vendors ABB, Siemens, Schneider Electric, General Electric, FLSmidth.
Lead Electrical Engineer
Jun 2013
— Feb 2015
Electrical Engineer
Jan 2012
— Jun 2013
Foreman of electrical laboratory
Aug 2011
— Dec 2011
Electrical technician
Feb 2008
— Aug 2011