Construction, Commissioning, Operation of Water, Waste Water & Solid Waste Treatment Plants


Last Updated: 25th July 2017 (over 5 years ago)

Address
Larisa, Greece

E-mail
Locked

Phone Number
Locked

Gender
Male

Age Range
45 to 54

Qualification Level
Masters

Languages
English, Greek

Summary

A QUALIFIED ENGINEER AND ACCOMPLISHED CONSTRUCTION-COMMISSIONING AND OPERATION MANAGER
with 23 years’ extensive experience on challenging State-of-the-Art Environmental
Projects (Industrial, Drinking Water, Waste Water & Solid Waste Treatment) – who offers :
• Expertise in Construction Management, Project Management and Site Management.
• Erection, Operation & Maintenance skills (heavy electro-mechanical equipment).
• Strong construction, pre-commissioning, commissioning and start-up skills.
• Detailed engineering, planning and process fine-tuning competence.
• Fault diagnosis and technical trouble-shooting talents.
• Team leadership and personnel training capabilities.
• An excellent knowledge of international markets (particularly procurement for environmental projects).
• Administrative proficiency – flow charts, feasibility studies, purchase agreements, plant user manuals, etc.
• Computer literacy – AutoCAD Mechanical, Autodesk Inventor, Microsoft Office

Education

Mining University of Leoben (MUL), Austria
Research Engineer

   Sep 1990
— Jun 1991

National Technical University of Athens (NTUA)
Chemical Engineer

   Sep 1983
— Jul 1990

Diploma of Engineering (5years), Field of studies: Chemical Engineering

Experience

HELECTOR SA
Commissioning Manager and Operation Manager

   Nov 2016
— Current

Commissioning Manager during the trial period and then Operation Manager of the "Municipal Solid Waste Recycling and Composting Facility of Kozani, Greece, responsible for the commissioning and then for the commercial operation of the Plant. Plant capacity: 120.000tns of Municipal solid Waste/year.
Location: Kozani, Greece

HELECTOR SA
Construction Manager Mechanical, Deputy Contractor Representative, Commissioning Manager and Operation Manager

   Jan 2014
— Oct 2016

Construction Manager Mechanical, Deputy Contractor Representative, Commissioning Manager and Operation Manager for the project “Construction of the Mechanical Biological Treatment Plant of Sofia, Bulgaria for the treatment of Municipal Solid Waste in order to produce RDF”, responsible for the construction, commissioning and trial operation of the plant. Yellow FIDIC project, plant capacity 410.000tns of Municipal Solid Waste /year, budget 90.000.000€.
Location: Sofia, Bulgaria

Construction Company Christopher Constantinidis SA
Site Manager and Deputy Project Manger

   Aug 2009
— Dec 2013

Site Manager and Deputy Project Manager for the project: “Construction of Sludge Drying Plant of the Waste Water Treatment Plant of Thessaloniki". Budget 17.000.000,00€.
Location: Thessaloniky, Greece

Hniochos Ltd
Project Manager and Site Manager

   Jan 2008
— Jul 2009

Project Manager and Site Manager for the project "Construction of Extension of the Waste Water Treatment Plant of Lavrion". Budget 2.000.000,00€.
Location: Lavrion, Greece

Construction Company Christopher Constantinidis SA
Maintenance Manager

   Apr 2005
— Dec 2008

Maintenance Manager for the project: “Operation and Maintenance of the Waste Water Treatment Plant of Thessaloniki”. Plant capacity 160.000-200.000 m3/day, installed power 9MW
Location: Thessaloniki, Greece

Edrasis Psallidas SA
Construction Manager

   Jun 2004
— Mar 2005

Construction Manager for the project: “Engineering, Erection and Operation of Plant Extension in the Waste Water Treatment Plant of Karditsa, Greece”. Budget 3.000.000,00€.
Location: Karditsa, Greece

J&P Joannou & Paraskevaides Overseas Ltd
Mechanical Project Engineer

   Dec 2003
— May 2004

Mechanical Project Engineer for the project: “F-NC 174 Elephant Field Development – Pipeline Contract”. Construction, hydro testing and commissioning of 24’’ (76km) and 16’’ (10km) crude oil pipelines at Mesak Setafet area (J&P camp: Lasmo) of Libyan Sahara. Client: Agip Oil Ltd.
Location: Mesak Settafet at Lybian Sahara Desert, Lybia

Envitec SA
Construction Manager and Site Manager

   Jan 2003
— Dec 2003

Construction Manager and Site Manager for the project: “Construction of Odor Control System at the Recycling and Composting Plant for Municipal Solid Wastes at Ano Liosia, Athens”. Budget: 10.000.000,00€.
Location: Athens, Greece

Envitec SA
Construction Manager and Site Manger

   Jun 2001
— Dec 2002

Construction Manager and Site Manager for the project: “Construction of Recycling and Composting Plant for Municipal Solid Wastes at Ano Liosia, Athens Recycling Plant of Ano Liosia, Athens”. Budget: 67.000.000,00€. Plant capacity: 1200 tn/day, installed power 12 MW.
Location: Athens, Greece

Envitec SA
Construction Manager

   Sep 1998
— May 2001

Co-ordination of the design and the construction of machinery for solid waste treatment for the project: “Construction of Recycling and Composting Plant for Municipal Solid Wastes at Ano Liosia, Athens”. In particular:
 Rotary screens (11 pcs). Total weight: 360tn. Hydraulic drive. Budget: 1.300.000,00€. .
 Compost turners (6 pcs). Total weight: 360tn. Hydraulic drive. Budget: 2.600.000,00€.
 Mixers (3 pcs). Total weight 45 tn. Hydraulic drive. Budget: 147.000,00€..
 Installation of rails. Total length:5.7km. Total weight: 300tn. Budget: 235.000,00€.
 Feeders (12pcs). Total weight: 80tn. Budget: 293.000,00€.

Duties:
 Definition of process requirements.
 Calculation and selection of mechanical and hydraulic driving elements.
 Correction of drawings.
 Detail engineering.
 Market research in Greece and abroad and selection of suppliers.
 Contract preparation in Greek and English.
 Follow up of contracts in Greece and abroad.
 Installation and commissioning of equipment

Location: Athens, Greece

Envitec SA
Construction Manager and Site Manger

   Oct 1996
— Aug 1998

Construction Manager and Site Manager for the project: “Construction of the Municipal Solid Waste Composting Plant of the City of Kalamata”. Budget: 3.200.000,00€. Plant capacity: 80 tn/day.

Duties:
 Supervision of subcontractors.
 Supervision of the installation of steel constructions, buildings, machinery (belt conveyers, chain conveyors, bridge cranes, shear shredder, trommel and vibrating screens, ventilators, pumping units and mixing equipment).
 Plant commissioning and process fine tuning.
 Personnel training and plant operation.

Location: Kalamata, Greece

Envitec SA
Deputy Site Manger and Operation Manager

   Sep 1994
— Sep 1996

Deputy Site Manager and Operation Manager for the project: “Construction of the Potable Water Treatment Plant of the city of Patras”. Budget: 2.900.000€. Plant capacity: 2600m3/hr).

Duties:
 Personnel management (workers and technicians).
 Cash management.
 Commissioning and process fine tuning.
 Installation and calibration of process instruments (turbid meters, suspended solids analyser, PH - analyser, flow meters, ClO2 - analysers, conductivity-analyser, differential pressure transmitters, pressure transmitters, level indicators and level switches).
 Coagulant dosing.
 Quality control.
 Start-up, flow chart modifications and operational tests of PLC units and SCADA software.
 Personnel training.
 "Plant User Manual" preparation.

Location: Patra, Greece

Natinal Technical Univercity of Greece (NTUA)
Research Engineer

   Aug 1991
— Sep 1993

Research Engineer at the National Technical University of Athens, Department of Mining Engineering, on a project sponsored by the Greek General Secretariat for Research and Technology, concerning the feasibility of Enhanced Oil Recovery in Prinos Field, Kavala, Greece

Location: Athens, Greece

Mining University of Leoben (MUL), Austria
Research Engineer

   Sep 1990
— Jul 1991

Research Engineer at the Mining University of Leoben (Austria), Institute of Drilling and Production of Oil, on a project sponsored by Western Petroleum Services, concerning Enhanced Oil Recovery by means of acid injection.

Location: Leoben, Austria