Lead Mechanical Engineer/commissioning Manager for water and power plant stations.
Last Updated: 7th February 2018 (over 4 years ago)
Summary
Education
Bsc Mechanical Enginnering
Oct 1988
— Jun 1993
Experience
Senior Mechanical Engineer
May 2009
— Feb 2018
• Capability study for contractors/suppliers.
• Review as built drawing and initiate the approval.
• Supervision of construction and commissioning of new Equipment.
• Site Schedule development, monitoring and updating.
• Prepare the necessary budget to update and improve the existing stations.
• Estimate the efficiency of equipment.
• Prepare technical documents and ensure compliance with ISO Quality
Procedures.
• Review O&M for new stations.
Senior Mechanical Engineer
Jan 2007
— May 2009
• Supervision the construction and commissioning of the following (EPC
contract);
- 9 Steam Generators (475 t/h), 5 Steam Turbines 120 MW and
Demineralization plant.
- Auxiliary systems including rotary equipments , Pumps, Piping,
compressors, Heaters and Flue gas Treatment Systems, (Electrostatic
Precipitator, Absorber), Diesel generator, Piping…. .
- RO Desalination Plant, 168,000 t/day (16 Trains)
• Review the construction and commissioning schedules.
• Review as workshop and as build drawings and modifications advice.
• Inspection of all mechanical activities and equipments (piping hydro testing,
rotary equipment alignment, ….etc.) according to standards.
• Follow up and control the site activities and progress.
• Inspection of work completion and issue the RFI’s & Test Packages.
• Review the material and mechanical equipment specifications.
• Supervision of construction and commissioning activities.
• Site Schedule development, monitoring and updating.
• Participating in HAZOP study.
• Prepare the weekly and monthly reports.
• Handing over the systems for start up and operation.
• Control the interface points between the power and petrochemical project
(HHP, HP, MP, LP process steam lines).
Senior Mechanical Engineer (Power Plant Specialist)
Aug 2006
— Jan 2007
plants.
• Review the tenders documentations.
• Feasibility studies for power and desalination plants.
• Development of plant and system concepts.
• Specification preparation for major mechanical equipment and bid evaluation.
• Review prequalification for vendors.
• Review the design drawings.
• Review the materials specifications and selection.
• Prepare project management files for projects.
Project and Research Engineer
May 2005
— Jul 2006
750 MW).
• Review the as build drawings.
• Compiling contract documentation and conditions of contract.
• Analysis of the performance Indicators and factors for the Power plants of the
East Delta company.
• Review the performance and efficiency for Talkh Power plant (2 conventional
units and 8 gas turbine units).
• Prepare the BOQ and mechanical specifications.
• Review the tenders documentations.
• Technical Proposals.
Senior Operation Head Section for Ayoun Moussa Power Plant
Aug 2004
— Apr 2005
• Control the operation and stability of the plant.
• Outage manager for the plant.
• Training the new staff.
• Analysis the trouble shooting and issue the accident reports.
• Prepare the operation Procedures.
• Plant manager shift.
Warranty Deputy Manager
Sep 2003
— Jul 2004
• Planning for outage jobs.
• Ensure that optimum Project Strategy is developed.
• Preparing technical files to perform the job
• Coordination with the operating company.
• Engineering reports and modifications advice if need.
• Apply all modifications for the units.
• Update and finalizing the systems design manuals.
• Finalize the outstanding items for the plant.
• Finalize the Final Acceptance Certificates.
Senior Commissioning Engineer for EDF Port Said Power
Oct 2002
— Aug 2003
capacity 1050 t/h) with EDF Egyptian Engineer company (Consultant
company) at Port Said power Plant.
• Construction completion inspection.
• Review the Boiler design drawings (Construction drawings – Logic diagrams –
Equipments power supply and emergency power supply) and modify if needed
after Foster Wheeler design office agreement.
• Review the schedule of activities with the contractor (FW).
• Attend commissioning technical meetings.
• Commissioning and prepare all the systems for start up and operation and
apply all the tests and protections.
• Prepare the boiler Emergency procedure.
• Handing over the plant for commercial operation.
• Witness the plant performance tests.
• Schedule control and development.
• Apply several walk down and punch lists.
• Ensure completion of Project on time and complying to HSE and Quality
Standards.
Construction Coordinator/Commissioning / Shift Charge Engineer for Ayoun Moussa power
Nov 1996
— Oct 2002
to the stage of Final Acceptance certificates.
• Witness the commissioning tests (Blow out, performance tests, ….)
• Handing over systems for operation.
• Safe start up and safe shutdown for two steam units 320 MW and MSF
desalination stations
• Prepare the defects and accidents reports.
• Carry out the work permits.
• Supervise the operators.
• Prepare operation flow charts.
• Coordination with maintenance to carry out the work permits safely.
• Prepare the operation procedures for the systems.
Maintenance Engineer
Jan 1994
— Jul 1996
marks of diesel engines Caterpillar, Perkins, Strover, .....
• Supervision the installation of diesel stations.
• Control the spare parts.
• Inspecting and test diesel stations.
• Planning for maintenance schedule.