Senior Planning Engineer


Last Updated: 22nd March 2018 (over 4 years ago)

Address
United Arab Emirates

E-mail
Locked

Phone Number
Locked

Gender
Male

Age Range
35 to 44

Qualification Level
Other Post Graduate

Languages
English, Gujarati, Hindi

Summary

Expertise in planning & scheduling the project by developing a project master schedule in line with the contractual requirements through the application of the Primavera P6/MSP

Proficient in preparing project management plan, identifying project deliverables, preparing construction methodology, milestones, tasks, determining resource requirements and allocating available resources to various phases of the project

Proven skills in preparing & monitoring of Detailed Construction Budget & S-Curves, Procurement & Drawing Schedules, Cost & Schedule Variance Reports, Resources Histograms, Dashboard Reports and Management Information System

Pioneered the preparation, monitoring and communication of project controls documents such as updated schedules, change requests, deliverables/milestones status, productivity analysis, risk register, material controls systems, and so on throughout the project life cycle

Recognized for planning, scheduling & monitoring of Oil & Gas, Infrastructure, Industrial, Residential & Commercial Projects as per project management framework, processes, budgeting, risk, cost monitoring systems, FIDIC and HSEQ procedures

Track record of managing Large Size EPC Hydropower, Roads, Water Supply, Industrial, High Rise Building, PEB Works, Oil & Gas and Villas Projects

Education

Project Management Institute (PMI)
Project Management Professional (PMP)

   Sep 2014
— Sep 2020

Project Management Professional (PMP) - PMP No. 1748863, Valid till 17th Sep’20

(National Institute of Construction Management and Research) NICMAR, Pune
Post Graduate Program in Advance Construction Management (PGPACM)

   Jul 2007
— Feb 2009

Post Graduate Program in Advance Construction Management (PGPACM)

Sinhgad College of Engineering, Pune University
B.E. (Civil)

   Jun 2003
— Jun 2006

Bachelor of Engineering - Civil

Bharati Vidyapeeth (MSBTE), Pune
Diploma - Civil

   Jun 1999
— Mar 2003

Diploma - Civil

Experience

GBH International Contracting (RMB Group)
Senior Planning Engineer

   Aug 2017
— Current

Project Title: The Fields Project, MBR City, Meydan, Cost-USD 330 MN, Duration- 2.5 Years

Description: The project included Construction of G+1 1028 Villas

Draieh Contracting (DAMAC Group)
Senior Planning Engineer

   Feb 2016
— Aug 2017

Title: Residential and commercial tower at Marina, Burj Damac Marina, Lusail City, Cost-USD 45.80MN, Duration- 2.5 Years
Description: The project included Construction of B+G+3P+23 & External Infrastructural Works.

Title: Residential tower at Marina, Burj Damac Water Front, Lusail City, Cost-USD 48.95 MN, Duration- 2.5 Years
Description: The project included Construction of B+G+2P+21 & External Infrastructural Works.

Title: Engineering, procurement & construction of the Helium 3 OSBL facilities and construction of helium 3 recovery facilities (helium 3 project), RasGas, Ras laffan Industrial City, Cost- USD 15.27 MN, Duration- 1.5 Year
Description: The project included Engineering, procurement & construction of Substation, Blast Resistance Control Building, Equipment foundations and Structural steel works.

AL Thabat Holding LLC
Planning Engineer

   Sep 2014
— Feb 2016

Title: Government Offices & Accommodation at Ibri, Cost-USD 09MN, Duration-1.5 years
Description: The project included buildings such as Office Accommodation, Club, Office, Villas, Prayer hall, Substation, Guard & Admin, VIP Accommodation, Guard Accommodation & External Infrastructural Works.

Title: Government Offices & Accommodation at Muscat, Cost-USD 15.5 MN, Duration-2 years
Description: The project included buildings such as Office Accommodation, Club, Office, Villas, Prayer Hall, Substation, Guard & Admin, Accommodation, Guard Accommodation & External Infrastructural Works.

Title: Construction of Perimeter Boundary Wall at Muscat, Cost-USD 5.2 MN, Duration-1 year
Description: The project included 4.6 KM with Watch Towers and Gates.

Title: Construction of Perimeter Boundary Wall at Mabella, Muscat Governorate, Cost-USD 7.40 MN
Duration: 1 year
Description: The project included construction of Boundary Wall (1.60KM), Normal Security Fence (5.2KM), High Security Fence (2.6 KM) and Admin. Building

Title: Government Offices & Accommodation at Mazyona, Cost-USD 8.6 MN, Duration-1.5 years
Description: The project included buildings such as Office Accommodation, Club, Office, Villas, Prayer hall, Substation, Guard & Admin, Accommodation, Guard Accommodation & External Infrastructural Works.

Title: Government Offices & Accommodation at Bhukha, Cost-USD 5.7 MN, Duration-1.5 years
Description: The project included buildings such as Office Accommodation, Club, Office, Villas, Prayer Hall, Substation, Guard & Admin, Accommodation, Guard Accommodation & External Infrastructural Works.

Kalyani Global Engineering (Bharat Forge Group)
Senior Planning Manager

   Jan 2011
— Sep 2014

Title: Manufacturing of Turbines Generators Plant (EPC Project), Cost-USD 73MN, Duration-2 years
Client: Alstom-Bharat Forge Power Limited
Consultant: Tata Consulting Engineers Limited (TCE)
Description: The project included Pre-engineering Building (PEB) with EOT Crane of 600 MT capacities, 14,000 MT of Structural Steel covering 76000 SqM area; 17 utility buildings with 2400 SqM built-up area for facilities like LPG, Compressed air, Oil, Chemical; major corporate administrative building; sub-station building with 25 MVA Transformers; 66 KV Switchyard; Fire Station; Boundary Wall and Railway Track Network.

Title: Bharat Forge SEZ Infrastructure Development Work, Cost-USD 120MN, Duration-3 years
Client: Bharat Forge, Khed Economic Infrastructure Pvt. Ltd.
Description: The project included 50 KM of Road Network, Water Supply, Boundary Wall and Electrical Substations.

Title: Second Casting Facility at ISRO, Cost-USD 8MN, Duration-2.5 years
Client: Indian Space Research Organization (ISRO)
Description: The project included second casting facility at ISRO- High Bay, Low Bay, Casting Well, VVVF Room, Deluge Room & Mechanical Works.

Hindustan Construction Company (HCC)
Planning Engineer

   Mar 2009
— Jan 2011

Title: Kishanganga Hydroelectric Project – EPC Civil, Hydro Mechanical and Electro Mechanical Works for 330 MV Hydropower Project, Cost-USD 550MN, Duration-7 years

Client: National Hydro Power Corporation (NHPC)
Consultant: Halcro
Description: The project included engineering, procurement and construction of CFRD Dam and Intake Structure, 20.5 km HRT by DBM & TBM Method, Surge & Pressure Shaft and Underground Power House with 3 units of 110 MW Turbines and Tail Race System.

Mahindra Gesco
Site Engineer

   Sep 2006
— Jun 2007

Title: Mahindra Royal Residential Township, Cost-USD 36 MN, Duration-3 years
Client: Mahindra Gesco
Description: The project included construction of 12 high rise residential building of 1 million sq. ft.