Summary

- 9 years experience on complex projects in energy sector - nuclear - as schedule engineer / project engineer
- 4 years experience in automobile industry as project engineer
- Experience in Engineering / Construction / Commissioning / Dismantling
- PRIMAVERA P6 / MS PROJECT / MS OFFICE proficient
- Worldwide mobility

Experience

AREVA
Commissioning Scheduler

   Feb 2016
— Sep 2018

Commissioning Time Scheduler for OL3 EPR Nuclear Plant

RESPONSIBILITIES
- HVAC Commissioning Schedule
- WASTES Systems Commissioning Schedule
- Nuclear Fuel HANDLING Mechanical Equipment Commissioning schedule
- Emergency DIESELS Groups Commissioning schedule
- NUCLEAR FUEL Manufacturing schedule

ACHIEVEMENTS
- Schedule consolidation / analysis / follow-up
- Sub-critical & critical paths identification
- Schedule risk analysis
- Total Float management
- Resources allocation & workload management
- Reporting to Project Direction

ASSYSTEM
Construction & Commissioning Schedule Engineer

   Jun 2014
— Feb 2016

Construction, Erection & Commissioning Schedule manager for STEMA project - Radioactive and liquid wastes treatment plant (CEA Marcoule) - Budget €80 million

RESPONSIBILITIES
- Construction, Equipments & process Erection, Commissioning phases scheduling and follow-up
- Works Coordination Department organization
- Schedule reporting (internal and towards Customer)

ACHIEVEMENTS
- Strategic schedule
- 3 months look ahead Works and Commisioning schedule
- Implementation of plant commissioning strategy

ASSYSTEM
Project Engineer

   Apr 2013
— May 2014

Engineering of a new built fuel rods storage building & reactor building civil works reinforcement (CEA Cadarache - MASURCA)

RESPONSIBILITIES
- Detailed studies schedule implementation, follow-up and reporting
- Contribution to cost control / changes management

ACHIEVEMENTS
- Deliverables list identification and scheduling
- Project control database development & implementation

SOFINEL
Engineering Schedule Engineer

   Dec 2010
— Mar 2013

Global engineering studies planner for Nuclear Island on Bristol UK EPR project

RESPONSIBILITIES
- To achieve the detailed engineering schedules
- To define and implement reporting tools
- To define and implement scheduling process

ACHIEVEMENTS
- 7 detailed engineering schedules implementation preparation on PRIMAVERA P6 (over 7 000 tasks for 2011-2013 period)
- 4 dashboards gathering indicators relative to project progress
- Monthly contribution to progress report issuance to Customer

CEA
Dismantling Schedule Engineer

   Apr 2009
— Nov 2010

Works Coordination Department planner for PHENIX reactor dismantling project (CEA Marcoule)

RESPONSIBILITIES
- To achieve detailed schedule on two reactor dismantling works
- To run schedule meetings
- To initialize the Organization Memo for the Works Coordination Department

ACHIEVEMENTS
- 2 effective detailed schedules and related assumptions notes (over 5000 tasks)
- Proposal and implementation of Organization Memo for the Works Coordination Department

PSA PEUGEOT CITROEN
Project Engineer

   Nov 2005
— Mar 2009

C3 PICASSO Assembly Process Project Manager’s Deputy

RESPONSIBILITIES
- To prepare the organization of project phases (prototype, pre serial, production line shift)
- To ensure project baseline, broadcast and implement the project control process
- To contribute to project costs management (€11 million budget)
- To contribute to project resources management (up to 35 people)

ACHIEVEMENTS
- Prototype and pre serial assembly organization and supervision
- 138 indicators set, implemented and followed-up through 7 dashboards, including resources management
- Follow-up of special means of production development, providing and start-up (80% of budget)