Senior Project Planner with 13 years experience


Last Updated: 25th July 2018 (over 4 years ago)

Address
South Africa

E-mail
Locked

Phone Number
Locked

Gender
Male

Age Range
25 to 34

Qualification Level
None

Languages
Afrikaan, English

Summary

Senior Project Planner with over thirteen years’ experience in the management, cost control and planning of multi-discipline capital expenditure projects from conception to commissioning, final take-over and rollout of guarantee periods. Project disciplines included various combinations of mechanical, civil/structural, EC&I, piping (HP & LP), etc. in the materials handling, power generation & mining infrastructure.

Education

Afrikaans High School Sasolburg
Matric

   Jan 1999
— Nov 2003

LAST SCHOOL ATTENDED: Afrikaans High School Sasolburg
HIGHEST STANDARD PASSED: Matric,
SUBJECTS PASSED: Afrikaans, English, Maths, Science, Biology, Geography, Physiology

Experience

Murray & Roberts Power and Energy - Medupi Power Station
Senior Project Planner

   Apr 2015
— Current

Develop WBS/detail construction- and on-site component assembly activity level CPM schedules for Boiler units 1 to 5 structural (structure and ducting), piping (boiler pressure parts, integral, HP & LP), and mechanical (Gas Air Heater ID, PA & FD Fans, Mills, Feeders) as part of the Medupi power station project. Reporting progress S-curves, deviations and slippages. Delay Analysis to assist Change Management and Commercial Teams.
Supervise and mentor the activities of 4 Planners and 1 Junior Planners
Develop day-to-day activity lists (Level 4 schedule) for construction teams
Report progress and earned value

Exxaro - Mpumalanga Commercial Mine Projects (Leeuwpan)
Lead Project Planner

   May 2012
— Mar 2015

I was placed in charge to manage/overseeing over 60 Projects on Leeuwpan Coal mine that include creation of WBS,CBS, Baseline, Resource Loading, and synchronize SAP WBS on the projects to EPM (Enterprise Project Management) system. On a weekly basis updating, tracking progress and scheduling meetings with project managers. I made use of the progress/tracking information to update the MS Projects schedule that updates the EPM system to generate histograms, S curves and reporting back to Exxaro Management

Steval Engineering - Zambia Konkola Copper Mine Project
Project Planner

   Nov 2011
— Apr 2012

On a weekly basis going on site and taking progress for e.g. tracking of the erection process measuring total steel work installed, meters of pipe work installed, mechanical equipment installed etc. I made use of the progress information to update the MS Projects plan (Time Schedule) using the time schedule to create Histograms, S curves and reporting back to Steval Planning Manager

Genrec Engineering - Germiston Wadeville Medupi and Kusile Power Stations
Project Planner

   Feb 2009
— Sep 2011

Tracking progress of projects and using tracking sheets to update the primavera schedule. On a weekly basis reporting progress to the client.

Imbabala Contracts - PPC Pretoria Crusher Expansion Project
Project Planner

   Mar 2008
— Jan 2009

On a weekly basis going on site and taking progress for e.g. tracking of the erection process measuring total tons of steel work installed. I made use of the progress information to update the Primavera Project plan (Time Schedule) using the time schedule to create Histograms, S-curves etc. On a weekly basis I was also responsible to report all progress to client (Linde)

De Beers (Murray and Robberts MEI) - Voorspoed Diamond Mine
Project Planner

   Sep 2006
— Feb 2008

I was in charge of progress tracking for the following buildings: Primary Crusher, Primary Conveyor, Secondary Crusher, Tertiary Crusher and Scrubbing and Screening. On a weekly basis going on site and taking progress for e.g. tracking of the erection process measuring total steel work installed, meters of pipe work installed, electric cables etc. I made use of the progress information to update the Primavera Project plan (Time Schedule) using the time schedule to create Histograms, S curves etc. On a weekly basis I was also responsible to report all progress to client (De Beers Mining)

Murray and Roberts MEI - Poly Propylene 2 (PP2)
Junior Planner

   Aug 2004
— Aug 2006

Going on to site and taking progress for e.g. tracking of the erection process measuring total steel work installed, meters of pipe work installed, electric cables etc. I made use of the progress information to update the Primavera Project plan (Time Schedule) using the time schedule to create Histograms, S curves etc.

Murray and Roberts MEI - Sasol Polypro 3
Junior Planner and Material Control

   Nov 2003
— Jul 2004

I was in charge of all the material in the stock yard including the stacking, storing and tracking of material on a day to day basis, as a junior planner working under Keith Behr (Senior Project Planner) I had to produce reports on a weekly basis such as Resource Histograms, S curves, Bar charts etc.