Summary

Currently I am a Project Engineer at Group Five Nuclear Construction Services for the Steam Generator Replacement Project at Koeberg Nuclear Power Station. I am responsible for the compiling of engineering documents and site implementation documents from the engineering design documents, on the High Pressure Piping.
Previously I fulfilled the position of a Boiler High Pressure Piping & Pressure Parts System Engineer at Kusile Power Station New Build Project. I also provided engineering support to multiple Eskom power stations. The support was design based according to American (ASME) and European (BS EN) piping design codes.

Education

North West University Potchefstroom
Bachelor's Mechanical Engineering

   Jan 2011
— Nov 2015

Experience

Group Five
Project Engineer

   Feb 2018
— Current

Appointed at Group Five in the Nuclear Construction Services department in February 2018. As Construction Lead, responsible for High Pressure Piping on the secondary side (Main Steam and Feed Water) of the steam generator. Develops the documentation to implement the design in the construction phase in accordance with the rules for nuclear construction. Actions and roles executed in accordance with all regulatory, statutory requirements and American (ASME) Nuclear Construction
and Design requirements.
Highly involved in Non-destructive testing and welding documentation development. Additionally, exposed to heavy lift and rigging planning and documentation development.

Eskom Holdings SOC Limited Kusile Power Station New Build Project
Site Construction Engineer for Boiler High Pressure Piping and Pressure Parts

   Nov 2016
— Current

Site Construction Engineer for Eskom Holdings (SOC) Limited on the New Build Project of Kusile Power Station. I execute the position as the Boiler High Pressure Piping and Pressure Parts system engineer. I provide engineering in all phases of the project, from construction, commissioning to optimization and maintenance.

Eskom Holdings SOC Limited
Boiler High Pressure Pipiing & Pressure Parts Engineering In Training

   Feb 2016
— Oct 2016

Provided engineering support to multiple Eskom power stations. The support was design based according to American (ASME) and European (BS EN) piping design codes.