Project Engineer, Power plant Engineer


Last Updated: 28th March 2018 (over 4 years ago)

Address
Nigeria

E-mail
Locked

Phone Number
Locked

Gender
Male

Age Range
35 to 44

Qualification Level
Degree

Languages
English

Summary

I am a certified Lean Six Sigma Black Belt power plant Professional, with more than 11 years leadership experience in control room operations of power generation stations, power plant projects management and planning. I have worked with high profile global organizations in fast-paced projects. Both resourceful and proactive, I combine excellent leadership, oral, written and communication skills, with strong technical capability.

Education

Lagos State University
Mechanical Engineering

   Feb 2001
— Aug 2007

Experience

The AES Corporations
Shift Charge Engineer

   May 2014
— Dec 2016

 As an owner’s engineer, I planned and managed the Amman-Jordan Middle East's installations, operation and maintenance activities of two power plants; a $360 million simple-cycle heavy fuel oil/gas-fired power plant (250 megawatts) and a $300 million (380 megawatts) CCGT (Ansaldo gas turbine and Fuji steam turbine) power plant, and ensured that both plants operational performance was optimized and ensuring the Power Purchase Agreement was not breached.
 I managed a power generation control room, operation team that delivered monthly power generation sales of more than $10 million, and generates more than 90% of plant dependable capacity.
 I was the shift in charge of the power generation/operation team and led 48 power plant operation professionals, and supervised the control room activities, root cause analysis of power generation defects, and continuous improvements using Lean Six Sigma.
 I took charge of critical decision making and most times, acted as the plant manager where I championed Health, Safety, and Environment as the day/night shifts highest priority to ensure compliance with safety and environmental procedures.
 I examined accidents to obtain data that can be used to design adequate preventive measures, as well as created, updated, and maintained standard operating procedures.
 I prepared technical scopes of work, correspondence, and documentation that supported effective design, development, and implementation of power station engineering change packages, and supervised log sheet records, BOP parameters and daily reports.
 I provided engineering support including training to field, operations and improvement engineers and supervised all Lockout and Tagout activities of safety.
 I led the setup and operation of The AES Corporations Amman business units and collected data on root causes of failures, process variations, and defects, and created improvement measure to improve performance.
 I directed operation and maintenance activities of the power plants to ensure efficiency and conformity to safety standards, and delegated assignments to subordinate team leaders.
 I identified process inefficiencies through gap analysis and benchmarking, and recommended/initiated improvement measures
 I was responsible for increased annual revenue by 10% by recommending improvements in efficiency using the CCGT fogging systems improvement project.

Paras Energy Limited
Senior Power Plant Engineer

   Oct 2010
— Apr 2014

 At the 110-megawatt gas power plant facility, I led a team of experienced professionals to the successful construction and commissioning of $120 million power plant projects and supervised all operation, performance and maintenance activities for four (4) years.
 I planned and managed improvement projects, and prepared materials costs and timing estimates, as well as reports and design specifications for the asset.
 I maintained the excellent relationship between the company and clients and successfully secured a two-year contract extension for the company, with a revenue increase of 7%.
 I established operational objectives and work plans and delegated assignments to subordinate engineers.
 I provided technical support during construction, startup, testing, system commissioning and performance monitoring, and ensured that all safety regulations and standards were followed as a standard practice.

Shoreline Power Company Limited
Performance Engineer

   Mar 2009
— Oct 2010

 At the 70-megawatt power plant, I was responsible for more than $1 million (capacity and variable operation and maintenance cost) monthly company power sales.
 I was in charge of employees training, continuous improvement projects review and selections, and led a team of 12 engineers to the successful commissioning of the $67 million gas-powered power plant.
 I coordinated project meetings and decisions across internal departments and teams and directed planning, budgeting, contractors’ selection and quality assurance efforts.
 I recommended process and systems improvements such as the 'all staff APEX projects' initiative that I brought up.
 I created alternative business plans to improve customer relationships.
 Led project scheduling and budgeting successfully and quickly completed engineering projects.
 Performed root cause analysis gas-fired power generators component failures.